EASA Means of ComplianceFinal — current published edition checked

MOC-2 SC-VTOL

Means of Compliance with SC-VTOL — Batch 2

Issue 3 — FINAL Source checked 2026-11-28

Scope, source and reading notes

Complete final batch 2 of SC-VTOL means of compliance. Later batches may amend individual provisions in earlier batches.

Aerospace Consulting reference note: Second final batch of means of compliance. Adds and revises earlier material; MOC VTOL.2105 was excluded from this final publication for further revision.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 1fcaf1c7db56acce38f5379ba2117f1137dbc35be3fa6ee4136a0f572d856136

Source page 65 · PDF page 65

Doc. No: MOC-2 SC-VTOL Issue: 3 Date: 22 Dec 2022

Condition VTOL

MOC - SUBPART E – LIFT/THRUST SYSTEM INSTALLATION

MOC VTOL.2400(c)(3) Lift/thrust system installation – likely hazards in operation

The likely hazards in operation, including hazards to ground personnel, that the applicant must account for should include:

(a) Risk of inadvertent electric motor start (if applicable): The aircraft controls should prevent inadvertent sudden motor operation when not commanded by the pilot, in particular during the aircraft supply power-on.

(b) Rotor/propeller disk conspicuity during landing, take-off and ground operations (if applicable): CS 27.1565 Amdt. 6 is accepted as a means of compliance for rotors, propellers and other rotating parts that could hit and injure ground personnel. Considerations for night conditions should also be included if night operations are authorised.

(c) Downwash effect on third parties: The downwash of the aircraft should be characterised and reported to allow safe operation and minimisation of hazards to ground personnel. The following method can be followed to test and report aircraft downwash:

Preliminary assessment: The applicant should assess whether the test as described in this section can be conducted safely for his aircraft. Test: While the aircraft is in a low hover, the radial component of the downwash (outwash) is measured around the aircraft on a circle of diameter 2 D. Reporting: The maximum measured speed is reported in km/h to the nearest multiple of 5, as well as the measurement standard (here “§(c) in MOC VTOL.2400(c)(3)”), in the performance section of the aircraft flight manual. If the downwash temperature on the 2 D-diameter circle is more than 10°C above ambient temperature, this should also be characterised and reported. Note: ‘D’ is reported as part of MOC VTOL.2115. Test specification:

≤ 3 kt -

Parameter Description Value Tolerance Conditions density altitude ≤ 2000 ft - ambient wind, throughout each test run, measured 2 m above the ground within 200 m of the circle centre. Location

should be representative of the test condition.

≤ 2 cm -

no precipitations - - Surface Smooth pavement, e.g. concrete or asphalt, surrounded by clear area, e.g. grass (Figure 1) diameter pavement ≥ 3 D - diameter clear area ≥ 6 D naturally occurring height discontinuity on pavement (excluding measuring equipment and operator, e.g. joint

between concrete slabs)

View figures, tables and original page layoutOriginal source page Source page 65 · PDF page 65 of MOC-2 SC-VTOL

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

SC-VTOL-02

Related technical context

Engineering context
Evidence and scope

SC-VTOL-02 and MOC-2 SC-VTOL — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.