MOC-2 SC-VTOL
Means of Compliance with SC-VTOL — Batch 2
Issue 3 — FINAL Source checked 2026-11-28
Scope, source and reading notes
Complete final batch 2 of SC-VTOL means of compliance. Later batches may amend individual provisions in earlier batches.
Aerospace Consulting reference note: Second final batch of means of compliance. Adds and revises earlier material; MOC VTOL.2105 was excluded from this final publication for further revision.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 1fcaf1c7db56acce38f5379ba2117f1137dbc35be3fa6ee4136a0f572d856136
Doc. No: MOC-2 SC-VTOL Issue: 3 Date: 22 Dec 2022
Condition VTOL
Proper and adequate attempts to induce flutter have been made within the speed range up to VD; The vibratory response of the structure during the test indicates freedom from flutter; A proper margin of damping exists at VD; and There is no large and rapid reduction in damping as VD is approached.
(e) For modifications of the type design which could affect the flutter characteristics, compliance with (a)
should be shown, except that analysis alone, which is based on previously approved data, may be used to show freedom from flutter, control reversal and divergence for all speeds up to the speed specified for the selected method.
MOC VTOL.2250(c) No catastrophic effect from structural single failures in the Category Enhanced
Note: The following fully replaces (b) in MOC VTOL.2250(c) in Doc. No. MOC SC-VTOL, Issue 2
(b) Structural Failure Rate
For structural elements or parts and failure modes identified in (a)(5)(ii), if a quantitative assessment is not directly feasible, an acceptable combination of compensating provisions should be implemented that provides sufficient confidence to achieve the safety objective and is appropriate to address the failure mode that could result in catastrophic consequences.
In addition, the framework outlined below may be used to determine the Structural Failure Rate for the MOC VTOL.2240(d) assessment, if a quantitative assessment is not directly feasible.
It should address each of the three following aspects (1) to (3), for which a non-exhaustive list of examples is provided below for each aspect:
Design Robustness:
(i) Larger static safety margins (ii) Thorough proven understanding of the load distribution (iii) Natural frequencies far from the forcing frequencies (iv) Larger fatigue (safe life) margins (v) Damage tolerance demonstration of larger damages (vi) Low complexity of the design and a limited number of failure modes (vii) Design values based on a statistical A-basis (99% probability with 95% confidence) as a
minimum
Quality of the part
(i) Identification of key manufacturing parameters and processes that are strictly
controlled, the modification of which require OEM validation. (ii) Regular material batch testing throughout the life of the element or part (iii) Non-destructive tests (NDT) / Destructive tests (DT) of one sample from every batch
throughout the life of the element or part (iv) Non-destructive acceptance test of every article (v) Process control specimens or witness coupons (vi) Special assembly procedures or functional tests to avoid maintenance errors (vii) Sensitivity to production process variability is low or is taken into account in the design
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
SC-VTOL-02 and MOC-2 SC-VTOL — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source