MOC-2 SC-VTOL
Means of Compliance with SC-VTOL — Batch 2
Issue 3 — FINAL Source checked 2026-11-28
Scope, source and reading notes
Complete final batch 2 of SC-VTOL means of compliance. Later batches may amend individual provisions in earlier batches.
Aerospace Consulting reference note: Second final batch of means of compliance. Adds and revises earlier material; MOC VTOL.2105 was excluded from this final publication for further revision.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 1fcaf1c7db56acce38f5379ba2117f1137dbc35be3fa6ee4136a0f572d856136
Doc. No: MOC-2 SC-VTOL Issue: 3 Date: 22 Dec 2022
Condition VTOL
(i) constructed of materials capable to withstand the effects of a flame and/or sparks, heat,
pressure and hot parts ejection, not allowing backside burning, backside ignition, or significantly high temperatures that can result in additional fire hazard, (ii) constructed so that no hazardous quantity of fluid, gases, smoke, soot, particulate,
liquid metal or flame can pass from any Explosive Fire Zone to other parts of the VTOL aircraft, and (iii) resistant to the heat and pressure created by a thermal runaway of the battery capable
to sustain a fire, spark, arc or heat transfer so that the protected elements essential to perform the remainder of the flight can continue to perform their essential function.
The conditions in (f)(3)(i) and (ii) should be fulfilled for the complete duration of an accepted Thermal Runaway Test as per MOC VTOL.2440. In meeting this paragraph, account should be taken of the probable path of a fire as affected by the airflow in normal flight and vertical take-off and landing.
(g) Detection systems
Detection systems include but are not limited to: quick-acting fire, gases, overtemperature / undervoltage / overpressure sensors. For each EESS and lift/thrust unit, approved, quick-acting detectors should be provided in numbers and locations ensuring prompt detection of faults potentially leading to fire. Each detector should be constructed and installed to withstand any loads to which it would be subjected in operation. No detector should be affected by any oil, water, other fluids, or fumes, soot and corrosive gas that might be present. There should be means to allow crew members to check the functioning of each detector system electrical circuit. The wiring and other components of each detector system in an electrical energy storage system compartment should have appropriate characteristics for the associated fire zone. No detector system component for any fire zone (FWZ, DFZ or EFZ) should pass through any other fire zone, unless–
(i) It is protected against the possibility of false warnings resulting from fires in zones
through which it passes; or (ii) The zones involved are simultaneously protected by the same detector and
extinguishing systems.
View figures, tables and original page layout

Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
SC-VTOL-02 and MOC-2 SC-VTOL — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source