FAA Advisory circularActive

AC 21-40A

Guide for Obtaining a Supplemental Type Certificate

21-40A Source checked 2026-11-28

Scope, source and reading notes

Certification guidance for applicants seeking a supplemental type certificate; applicable regulations and FAA directives take precedence.

Aerospace Consulting reference note: A practical guide to the supplemental type certification process, planning, compliance data, testing, and continued-airworthiness considerations.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b003e6dd04d9c240fc7d352800b1d33ce9625136376138618d66652dd570673d

Source page 67 · PDF page 67

c. Applicant testing.

(1) Research and development flight tests are to ensure that the design changes comply with the applicable 14 CFR parts. We don’t participate in, or witness these tests. However, we will discuss them with you and offer guidance, so your tests can be made meaningful and safe.

(2) Base your flight test plans on your knowledge of the modification and development tests, and on the certification basis. Include recommended tests, instrumentation to be used, necessary safety equipment, data acquisition and reduction methods. We will issue the TIA upon approval of the test plan and the descriptive and compliance data, after we establish conformity with the data, and complete our risk management process.

Note: After you successfully complete the inspection and test requirements, submit your flight test report to us for review.

d. FAA testing may include repeating some tests, partially or completely, to verify compliance with the certification requirements. Our testing may be done by an FAA pilot or an authorized DER flight test pilot.

e. Before FAA testing, we (or our designee) do the installation conformity inspection of the modified aircraft used for flight tests. If we find discrepancies, you must correct them, plus repeat any test that could have been influenced by the discrepancy.

f. Current and accurate aircraft weight, and the center of gravity (CG) location, is extremely important to ensure that the modified aircraft can be loaded to the critical weight and CG limits for flight testing. The flight test aircraft should be weighed and witnessed by an FAA representative before testing begins. If appropriate, you can determine the aircraft weight and CG by analysis. We will verify the resulting weight and balance determination. After we find it accurate, use it for all subsequent flight test weight and CG calculations.

g. Securely restrain any temporary ballast necessary for flight testing, so it withstands the inertial loads caused by a survivable emergency landing. A preferred form of ballast is small, solid pieces of a high density metal (lead, cast iron, or steel) fixed to the structure or in a suitable container fixed to the structure. We don’t accept using passengers as ballast. FAA approval of ballast installation for FAA flight testing will be required before the TIA may be issued.

h. Instrument calibration, when required, should be done by an approved instrument repair inspector with calibration cards provided by the instrument supplier before the FAA flight test program Types of instruments to be calibrated may include altimeters, tachometers, temperature gauges, and airspeed indicators. Do the flight test within 3 months of calibration. However, on critical items, do the flight test within 30 days of calibration.

Note: You may have to calibrate the entire airspeed system before flight testing.

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 21.101-1B

Related technical context

Engineering context
Evidence and scope

AC 21-40A and AC 21.101-1B — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.