AC 21-40A
Guide for Obtaining a Supplemental Type Certificate
21-40A Source checked 2026-11-28
Scope, source and reading notes
Certification guidance for applicants seeking a supplemental type certificate; applicable regulations and FAA directives take precedence.
Aerospace Consulting reference note: A practical guide to the supplemental type certification process, planning, compliance data, testing, and continued-airworthiness considerations.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b003e6dd04d9c240fc7d352800b1d33ce9625136376138618d66652dd570673d
certification (PSAC) and submit it to us after we accept the certification plan, unless it is a previously approved software based on Technical Standard Order (TSO) authorization or other approval process. Detailed guidance for preparation of the PSAC is in RTCA, Inc. document RTCA/ DO-178, Software Considerations in Airborne Systems and Equipment Certification.
d. For systems that contain complex hardware, prepare a plan for hardware aspects of certification (PHAC) and submit it to us after we accept the certification plan. Detailed guidance for preparation of the PHAC is in RTCA, Inc. document RTCA/ DO-254, Complex Electronic Hardware.
2-10. The Project Specific Certification Plan (PSCP). The PSCP is the primary project management tool for coordinating activities between us and applicants who choose to implement the techniques and guidance described in The FAA and Industry Guide to Product Certification (the CPI Guide). You can find this guide at: http://www.faa.gov/aircraft/air_cert/design_approvals/media/CPI_guide_II.pdf.
2-11. Establish Certification Basis.
a. One of the first tasks in an STC project is defining a certification basis. The certification basis is the set of regulations, special conditions, equivalent safety findings, and exemptions to the rules that identify the airworthiness standards and other standards for which you must show compliance. You must demonstrate compliance with all elements of the certification basis to our satisfaction before we issue an STC.
b. For some significant STC projects we may develop an issue paper to define the project’s certification basis. We designate this as the G-1 issue paper. See chapter 3 of this AC for more details on developing the certification basis. The G-1 issue paper states the FAA’s position and your (applicant’s) position. When we reach an agreement with you, we prepare a conclusion, which becomes the STC project’s official certification basis.
c. The compliance checklist is a valuable aid for you and us to document which regulations apply to the project and how compliance is shown with each regulation. See figure 2-5 for a sample checklist.
2-12. Phase III. Compliance Planning. In this phase the FAA project team makes determinations on:
• FAA involvement.
• Using parts produced by technical standard order (TSO) authorization or parts manufacturer approval (PMA) in certification testing.
• Completed (project specific) certification plan.
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 21-40A and AC 21.101-1B — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source