FAA Advisory circularActive

AC 21-40A

Guide for Obtaining a Supplemental Type Certificate

21-40A Source checked 2026-11-28

Scope, source and reading notes

Certification guidance for applicants seeking a supplemental type certificate; applicable regulations and FAA directives take precedence.

Aerospace Consulting reference note: A practical guide to the supplemental type certification process, planning, compliance data, testing, and continued-airworthiness considerations.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b003e6dd04d9c240fc7d352800b1d33ce9625136376138618d66652dd570673d

Source page 37 · PDF page 37

Figure 2-3. STC Project Initiation Checklist

This checklist clearly communicates the requirements to be fulfilled for STC issuance. Checklist requirements should, at a minimum, be handled early in the process between the applicant, the ACO project manager/engineer, and the responsible MIDO office of the project.

a. Is the STC application form and certification plan complete?

b. Will the model applicability of the STC expand? If so, what can be done on the initial certification that will make later STC expansion easier?

c. Will the STC be “multiple” or “one only?” If a “one-only,” provide the serial number along with the product make and model.

d. For “multiple” STCs, installation instructions will be necessary. Sufficient information must be available to replicate the modification or installation. (14 CFR § 21.303.) Has a fabrication inspection system been defined?

e. Are ICA required? See chapter 5, subparagraph 5-3.i. and note.

f. Could an existing STC be applied, possibly eliminating this STC certification project?

g. What is the applicant’s schedule and has it been coordinated with the FAA?

h. Where will product modification take place? If modification is outside the United States, see chapter 10 of this AC.

i. Will any parts be fabricated outside the applicant’s facility? If so, what kind, where, and when will they be made? Qualification and conformity will be required. If parts are fabricated outside the United States, see paragraph 1-9 of this AC.

j. What is required for the conformity inspection process? The applicant is responsible for recording and reporting conformity inspection results on FAA Form 8100-1, Conformity Inspection Record, before the FAA conformity inspection. Early submittal of FAA Form 8130-9, Statement of Conformity, in-process conformities and the procedure for making the Request for Conformity, FAA Form 8120-10, is a necessity. Drawings should be FAA/DER approved before asking the FAA to conduct a conformity inspection. See 14 CFR § 21.33.

k. What kind of drawing system will be used? It should: include a drawing list; provide information required for the various types of drawings (detail, component, assembly, installation and so forth); describe the modification; list the materials and applicable specifications, processes such as heat treating, and protective coatings used; and provide the dimensions in enough detail to accomplish the modification. Any process specifications such as fiberglass work should be documented and reviewed by the FAA. New processes may have to be demonstrated to an FAA inspector. List the suppliers of materials.

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 21.101-1B

Related technical context

Engineering context
Evidence and scope

AC 21-40A and AC 21.101-1B — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.