AC 21-40A
Guide for Obtaining a Supplemental Type Certificate
21-40A Source checked 2026-11-28
Scope, source and reading notes
Certification guidance for applicants seeking a supplemental type certificate; applicable regulations and FAA directives take precedence.
Aerospace Consulting reference note: A practical guide to the supplemental type certification process, planning, compliance data, testing, and continued-airworthiness considerations.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b003e6dd04d9c240fc7d352800b1d33ce9625136376138618d66652dd570673d
and environments encountered in the service life).
l. Prepare electrical load analysis for the installation and electro-magnetic interference (EMI) reports as appropriate.
5-4. Drawing Package. The drawing package describes the manufacture and installation of all parts necessary for the modification. Identify all part contours, materials, manufacturing operations, dimensions, finish specifications, and other data, either directly on the face of the drawing or by reference to a process specification or other appropriate information. You should assign drawing numbers that follow a logical pattern.
Note: Drawings are a major portion of the descriptive data required for a multiple STC. All drawings should be DER or FAA approved before our acceptance and conformity inspection. See 14 CFR § 21.33.
5-5. Drawing Revision Levels.
a. Each revision level should identify the changes and approval dates on the drawing. These items should be reflected in the drawing list submitted with the drawing package for FAA approval.
5-6. Good Drawing Practices. Thoroughly check drawings for accuracy and completeness before submitting them to us. This will reduce the likelihood that we will return drawings with unacceptable errors to you for resubmission. See section 5-10.
5-7. Tolerances.
a. Note the standard manufacturing tolerances on the drawing. You may refer to American National Standards Institute (ANSI) Specification Y14.5, Dimensions and Tolerancing, 1994, for guidance.
5-8. Drawing List. Prepare and submit a drawing list, or master drawing list (MDL), with the drawings. Include installation instructions, any process specifications, drawing or document number, revision level, any engineering change orders in effect, the date prepared, and the approval dates of all material. See appendix 2.
5-9. Examples.
a. See appendix 2 for a drawing list and several sample drawings. This is one way of meeting drawing package requirements. Process specifications for plating and inspection, as well as the installation instructions, are included in the drawing list, and they are divided into installation and manufacturing data. A revision control page is shown, but may not be needed on a very short drawing list.
b. We also included drawing examples showing a detail part, a subassembly, and an
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 21-40A and AC 21.101-1B — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source