FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.

Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4

Source page 74 · PDF page 74

(4) Inspections. FAA manufacturing inspection personnel do conformity inspections before ground and flight tests. All unsatisfactory items must be resolved before conducting the test.

(5) Tests. After the applicant complies with 14 CFR 21.35(a), FAA personnel witness and conduct official certification tests. FAA designees may also witness or conduct the tests when authorized to do so.

(6) Outside Certification Branch Requests. The project CM section should request the geographically appropriate CM section to perform the conformity inspection if the TIA conformity is done by FAA personnel outside the project CM section’s geographic area. If the TIA test is to be conducted by FAA personnel outside the geographic area of the PCB, the PCB may delegate the witnessing (at their discretion) to the geographically appropriate certification branch.

s. Flight Test Conformity Inspections. The ground inspection physically verifies that the aircraft submitted for flight test meets the minimum requirements for quality, conforms with the technical data, and is safe for the intended ground and flight tests. The results are recorded together with any other data requested by FAA engineering and flight test personnel.

(1) Normally a progressive ground inspection is performed in three phases. This depends, however, on the complexity of the project. The three phases are: preliminary ground inspection, official ground inspection, and coordinated ground-flight inspection. See chapter 5, paragraph 5-15 of this order for detailed information on these three phases.

(2) The manufacturing inspector makes the initial acceptance of the test aircraft for FAA flight testing. The initial acceptance is based on the determination of the aircraft condition for safe operation and the testing to be conducted. The manufacturing inspector and the flight test personnel should establish a mutually agreeable system for informing the project manager of daily changes to the aircraft and any problems encountered during flight test.

t. Certification Flight Tests are used by the FAA to verify the flight test data reported by the applicant or to obtain compliance data for flight testing conducted concurrently with the applicant. These tests evaluate the aircraft’s performance, flight characteristics, operational qualities, and equipment operation. They also determine operational limitations, procedures, and pilot information. Certification flight tests are conducted under the TIA and may include flight, ground, and functional and reliability testing. ACs 23-8, 25-7, 27-1, and 29-2 provide guidance for certification flight tests. Also, for type certification testing of prototypes, the applicant provides first-pilot-checkout flight time for the FAA flight test and AED pilots assigned to the project before the FAA compliance flight tests. For more information, see chapter 5, paragraph 5-19 of this order.

u. Operational and Maintenance Evaluations (AED Responsibilities). The AEDs were established to meet FAA’s operations and maintenance responsibilities during the type certification process. The AEDs are comprised of operations and airworthiness inspectors who work directly with aircraft certification personnel to contribute an operational perspective to engineering activities. The AEDs advise manufacturers of applicable operational and maintenance requirements during the design and certification process and make recommendations to Flight Standards about flight training, inspection programs, and flight crew

Page 52 Par 2-6

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

FAA Order 8110.37G

Related technical context

Engineering context
Evidence and scope

FAA Order 8110.4C and FAA Order 8110.37G — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.