Scope, source and reading notes

FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.

Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4

Source page 120 · PDF page 120

inspection system, an explanation of how it ensures conformity, and (to maintain configuration control) documentation of the prototype configuration as design changes are incorporated. This information is essential, and it helps the manufacturing inspector develop a conformity plan with the proper level of involvement.

(d) The product’s complexity and effect on air safety are used to determine how much the manufacturing inspector needs to inspect and evaluate an item. The manufacturing inspector considers, for example, product designs using relatively new materials or methods of construction, manufacturing technologies, and destructive and nondestructive inspection techniques. In these cases, because there may not be well-established or industrywide recognized standards for ensuring process and quality control, the manufacturing inspector should adjust the conformity plan accordingly.

(2) Based on the aforementioned circumstances, the manufacturing inspector (in coordination with the applicant) should develop an appropriate conformity plan. The plan should focus on the following:

(a) Verifying the conformity of the critical and major characteristics of materials, parts, and assemblies.

(b) Evaluating process controls to ensure production of consistent and uniform products. The applicant may use statistical quality control methods for process evaluation. The FAA file should include records of such activity and complete descriptions of such statistical methods.

(c) Observing tests of important functional parameters of systems, modules, components, and completed products.

b. Areas of Consideration. Regardless of the applicant’s experience, manufacturing inspectors are responsible for determining that the applicant performed a complete conformity inspection. They also are responsible for determining the results of the inspections are properly recorded and reported on FAA Form 8130-9. In witnessing conformity inspections, the manufacturing inspector should consider the following:

(1) Materials.

(a) Were raw materials used in the fabrication process in conformity with the design data?

(b) Is evidence available to ensure the chemical and physical properties were identified and checked as appropriate?

(c) Is there documented evidence to show traceability from the raw material to the prototype part?

(d) Are there any part or process deviations recorded against the submitted design data (including material review dispositions)?

Par 5-3 Page 105

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

FAA Order 8110.37G

Related technical context

Engineering context
Evidence and scope

FAA Order 8110.4C and FAA Order 8110.37G — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.