FAA Order 8110.4C
Type Certification
8110.4C — Changes 1–7 incorporated (2023-10-20) Source checked 2026-11-28
Scope, source and reading notes
FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.
Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4
this, they may compare pre-test and post-test dimensions. The applicant should record the results.
e. Step 5 – After completing steps (1) through (4), the manufacturing inspector verifies the applicant’s inspection report and submits it to the certification branch project manager as an attachment to FAA Form 8100-1. This report should contain the results of the inspection, giving a comprehensive description of all defects, failures, wear, or other unsatisfactory conditions including photographs. The FAA cannot overemphasize the importance of this report that the certification branch uses for its evaluations.
f. Step 6 – The manufacturing inspector should also ensure that the applicant identified questionable parts and kept them in safe storage for review by certification branch engineering. 5-15. GROUND INSPECTION – AIRCRAFT.
a. Purpose of Ground Inspections. The basic purpose of the ground inspection is physically to verify the aircraft submitted for FAA flight test meets the minimum requirements for quality, conforms to the technical data, and is safe for the intended flight tests. The manufacturing inspector records the results with any other data requested by FAA engineering and flight test personnel.
b. Phases of the Ground Inspection. The ground inspection is normally a progressive inspection performed in three phases, depending on the project’s complexity.
(1) Phase I – Preliminary Ground Inspection. This phase includes all inspections that can be performed satisfactorily during development and construction of the prototype. The applicant should arrange to notify the manufacturing inspector promptly whenever they change components, systems, or installations previously cleared through the manufacturing inspector. The manufacturing inspector should then witness these re-inspections as necessary. When re- inspection creates undue duplication of effort because of numerous development changes, go to Phase II if practicable. Title 14 CFR part 21, Subpart B requires the applicant to submit a final FAA Form 8130-9 before testing.
(2) Phase II – Official Ground Inspection. This is the final inspection of the complete prototype and should be performed just before the FAA flight test. As far in advance as possible, manufacturing inspectors should work out detailed procedures for conducting inspections and testing for both phases. They should also coordinate these procedures with the applicant to avoid unnecessary delays and duplication of effort. This also ensures that all required inspections and tests are properly accomplished. To notify the manufacturing inspector that their aircraft is ready for inspection, applicants submit an FAA Form 8130-9. This is the applicant’s commitment that the aircraft is ready for FAA inspection and flight test.
(a) To give FAA flight test personnel enough time to prepare for the flight test, the manufacturing inspector should notify them when Phase II of the Official Ground Inspection starts.
(b) The applicant should prepare the aircraft for inspection by providing all necessary assistance, equipment, and data essential for the inspection. The applicant should
Page 120 Par 5-14
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
FAA Order 8110.4C and FAA Order 8110.37G — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source