FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.
Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4
2-3. CONCEPTUAL DESIGN.
FIGURE 2-3. TASKS DURING THE CONCEPTUAL DESIGN PHASE
Process Orientation ................................................................................ 2-3a Pre-Project Guidance ............................................................................. 2-3b Familiarization Briefing ........................................................................ 2-3c Certification Plan ................................................................................... 2-3d
a. Process Orientation [previously Familiarization TCBM]. An applicant seeking a TC approval is encouraged to contact the certification branch in their geographic area before submitting a TC application. During this initial contact, a certification branch project manager should discuss the type of requested approval with the applicant and assess the applicant’s knowledge of certification procedures. The project manager needs to conduct a process orientation for applicants who are unfamiliar with certification. The process orientation establishes a partnership with the applicant and provides an opportunity to develop an understanding of the type certification process as it applies to the applicant’s design. The orientation should explain the need for certification, the certification process, the FAA’s role, and the applicant’s responsibilities. For applicants choosing to implement the techniques and guidance described in The FAA and Industry Guide to Product Certification, this information becomes the foundation for the Partnership for Safety Plan (PSP). Depending on the applicant’s previous certification experience, the process orientation may be conducted by phone or in person.
b. Pre-Project Guidance (Regulatory and Policy Discussions). The FAA requires a TC application before providing full access to the FAA resources necessary to complete a project. However, before this application, the FAA responds to the potential applicant’s questions about the FAA’s procedural and technical requirements that may arise after the applicant’s process orientation. The certification branch will first direct the potential applicant to appropriate regulatory, policy, and guidance material, then, at the certification branch’s discretion, involve itself directly. Further involvement may be necessary to determine how unique or novel a proposed design is, or to research past policy applications. However, expect potential applicants to educate themselves as much as possible on the certification process. Finally, encourage potential applicants to give the certification branch an initial familiarization briefing soon after they commit to applying for a TC.
c. Familiarization Briefings give potential applicants an opportunity to describe their project to the certification branch before application. These briefings are intended for products the applicant is committed to bringing to market through type certification. The main purpose is to familiarize the FAA with the proposed design as it is currently known. Learning about projects before submittal of the application also allows the certification branch to consider FAA involvement and begin planning resources. Special emphasis should be placed on technical issues and unique or novel features. Beyond being briefed on the design features, expect to hear about the intended operation, major suppliers and unusual vendor relationships, reliance on approved equipment, project schedule, and reliance on designees or delegated organizations.
Par 2-3 Page 20
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
FAA Order 8110.4C and FAA Order 8110.37G — published scope