FAA Order 8110.4C
Type Certification
8110.4C — Changes 1–7 incorporated (2023-10-20) Source checked 2026-11-28
Scope, source and reading notes
FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.
Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4
b. Conformity Inspection. Title 14 CFR part 21, subpart B requires the applicant to allow the manufacturing inspector to perform conformity inspections on structural test articles while making and assembling the articles. The applicant must submit an FAA Form 8130-9 to the FAA before testing. Also, 14 CFR part 21 Subpart B requires that the final design submitted for FAA approval must include all changes found necessary as a result of the test. The configuration control system must also ensure that the applicant included all changes in the production drawings. This is the only way the manufacturing inspector can be certain that subsequent production articles conform to the tested articles.
c. Nonconformities. On an FAA Form 8100-1, the certification branch project manager or authorized DER must disposition any nonconformities found because of the conformity inspection. Because nonconformities affect structural test articles differently than they affect flight articles, the FAA strongly recommends the applicant clearly identify parts and assemblies destined for official structural testing. This should be necessary only when the applicant is manufacturing structural test articles concurrently with prototype flight articles. It is important that once manufacturing inspectors subject parts and assemblies to structural testing beyond limit load testing, they should clearly and permanently identify the parts and assemblies. This prevents their use in production products.
5-12. PROTOTYPE FLIGHT TEST ARTICLES – AIRCRAFT. During the fabrication process, manufacturing inspectors should begin determining the conformity of prototype flight test articles, including system checks. It is important flight test articles conform to the data in the TIA and the applicant’s statement of conformity. 14 CFR 21.33 requires applicants submit the FAA Form 8130-9 to the FAA before the applicant releases prototype flight articles for FAA flight test. They should alert the certification branch project manager about any nonconformities described under deviations, so the project manager can evaluate the nonconformities and decide how they affect safety and the validity of the test under consideration. The manufacturing inspector should also ensure the applicant has provided specific aircraft identifier and performance information to FAA air traffic control as required by paragraph 2-6h(1).
5-13. ENDURANCE TEST ARTICLES – ENGINES AND PROPELLERS.
a. Conformity Determination. As in the case of aircraft, determining the conformity status of test engines and propellers is an important part of the type certification project. Normally, only parts subject to distortion, fatigue, and wear are inspected for conformity and witnessed by the manufacturing inspector before and after the endurance test. Before the endurance test, the manufacturing inspector should coordinate with the certification branch engineer to identify the parts subject to inspection. The manufacturing inspector should note the condition of all surfaces subject to distortion, fatigue, and wear, and record the actual dimensions on the FAA Form 8100-1. Also, these and other critical parts should be serialized or otherwise positively identified for pre-test and post-test comparison. 14 CFR part 21, Subpart B requires the applicant to submit FAA Form 8130-9 before the start of FAA test.
b. Conformity Inspection. When the endurance test and teardown inspection ends, the manufacturing inspector should spot-check conformity of major and critical parts. They do this by witnessing the applicant’s inspection, giving particular attention to critical characteristics.
Page 118 Par 5-14
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
FAA Order 8110.4C and FAA Order 8110.37G — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source