FAA Order 8110.4C
Type Certification
8110.4C — Changes 1–7 incorporated (2023-10-20) Source checked 2026-11-28
Scope, source and reading notes
FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.
Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4
inappropriate, such as foreign type-validation flight testing, or tests in support of field approvals. In these cases, a letter will be prepared by the appropriate office authorizing participation by FAA flight test and manufacturing inspection personnel. In this letter, the office will specify in detail, what is to be accomplished. When applicant flight tests are performed early in a program (before the TIA), before an FAA conformity inspection is conducted, the resulting data may still be valid if it can be established that:
(a) Testing took place on an aircraft that was essentially identical to the article that is later conformed to the type design, and
(b) No significant changes were made between the time of the test and the subsequent conformity inspection.
(2) Conformity of Test Article with Type Design. Before starting any official flight tests, the responsible test personnel for the project and ground inspection personnel should verify that a conformity inspection has been conducted to ensure that the aircraft is in conformity with the design data appropriate for accomplishing the tests and the aircraft is determined to be safe for the flight intended. The manufacturing inspector must have documented any nonconformities. Flight tests should not start until the appropriate TIA issuing office issues a release and notifies the flight test personnel.
(3) Checkout on Test Aircraft. Test pilots for the assigned project arrange with a responsible official of the applicant’s organization for an adequate and agreed upon checkout in the applicant’s aircraft. They must complete the checkout before the FAA pilots conduct any official FAA flight tests. See Order 8110.41.
(4) Pilot-in-Command. The pilot-in-command is the applicant’s pilot (except for single place aircraft). The FAA pilot should emphasize the pilot-in-command responsibility as part of the pre-flight briefing.
(5) Spin Recovery Parachutes.
(a) Spin recovery parachutes should be installed on all aircraft requiring spin testing for certification. Also, the FAA may require these installations for other high-angle-of- attack tests on aircraft where inadvertent spins or deep stalls are likely during testing.
(b) The FAA will consider other types of spin recovery devices such as anti-spin rockets when the applicant proposes them. These systems have many unknown characteristics, which would require considerable engineering research and wind tunnel testing. The tail- mounted spin recovery parachute system has been proven to be an effective spin recovery system and is the preferred system. For help in sizing a spin chute, see NASA Technical Paper 1076, Spin-Tunnel Investigation of the Spinning Characteristics of Typical Single-Engine General Aviation Airplane Designs, dated November 1977.
(c) Certification branches must carefully evaluate a spin recovery system installation to determine its structural integrity, reliability, susceptibility to inadvertent or unwanted deployment or jettison, and adequate or redundant jettison ability. The chute size, porosity, riser length, and lanyard length should be designed following NASA recommended practices to
Par 5-19 Page 127
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
FAA Order 8110.4C and FAA Order 8110.37G — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source