FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.

Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4

Source page 66 · PDF page 66

(b) Materials and products conform to the specifications in the type design,

(c) Parts of the products conform to the drawings in the type design, and

(d) The manufacturing processes, construction, and assembly conform to those specified in the type design.”

(2) The applicant must submit FAA Form 8130-9, Statement of Conformity, attesting that the articles are in conformity with the proposed design. The FAA should receive these forms from the applicant before conducting any FAA conformity inspections. Only in this manner can the FAA ascertain that the test articles are true representations of the proposed test article (see 14 CFR 21.53(b)).

c. Applicant Test Plan and FAA Approval. The applicant must prepare a test plan when testing is necessary to show compliance to the regulations. The applicant should also submit the test plan early enough to allow the FAA time to review and approve the test plan before the start of the test. The test plan is used to ensure orderly and complete testing is accomplished. At a minimum, a description of the items to be tested and a list of all equipment necessary to conduct the test should be in the test plan. It is also important to include a description of how the equipment is to be calibrated (when calibration is required) and approved before the test, required conformities of the test article and test setup, a list of the specific airworthiness standards, a description of how compliance is expected to be shown, and a test procedure written in a step-by- step format with defined pass/fail criteria. After the certification branch engineer or FAA pilot approves the test plan, they request an FAA conformity inspection of the test article and test setup to ensure conformance to the engineering drawings and test plan.

d. Before Witnessing Engineering and Flight Tests. When witnessing official tests, the FAA-authorized witness will verify that the test procedures described in the applicant’s FAA- approved test plan are followed and that any data captured by test instrumentation appears to be valid data for the test in question. If the test is lengthy, witness at least the most appropriate or critical portions of the tests and conduct a post-test examination. If the certification branch engineer or pilot will not be able to witness the test, they will authorize another qualified certification branch engineer, FAA pilot, or DER; or request help from a manufacturing inspector to witness the test. See chapter 5, paragraph 5-10 of this order for a discussion of CM section inspectors witnessing tests.

(1) The minimum participants for witnessing the test are the FAA-authorized witness and the applicant’s knowledgeable representative who can perform the test. But there are some cases such as flight tests of certain single-seat aircraft, agricultural airplanes, and gliders, where the minimum number of participants can only be one person, the FAA flight test pilot, or their designated DER flight test pilot. After the test, the FAA-authorized witness must sign a record showing the results were obtained by properly following the approved test plan. This record should identify the test and include the results obtained, the decisions reached, and any recommendations made to the applicant. Add a copy of this record to the test report. This record is not a substitute for the applicant’s test report showing completion of the test plan.

(2) If a CM section inspector or DER is to be the witness, the certification branch engineer or pilot will provide them with the appropriate instructions and a reference to the applicant’s test plan. The FAA-authorized witness should not witness any tests without prior coordination with the certification branch engineer or pilot.

Page 44 Par 2-6

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

FAA Order 8110.37G

Related technical context

Engineering context
Evidence and scope

FAA Order 8110.4C and FAA Order 8110.37G — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.