FAA type-certification procedures for FAA personnel and relevant designees; consolidated publication incorporating Changes 1 through 7. Base publication catalog date: 2005-10-12; latest included change: 2023-10-20.
Aerospace Consulting reference note: Describes the type-certification process and coordination of design approval, including compliance findings, testing, and certification documentation.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 12d96559b86bef5eba9ba2ac0309a8ca58c0121b7055a6238b867bda7dbd5dd4
inspection representatives, which include DMIRs, DARs, or ODARs. This streamlining also makes better use of FAA personnel and designees.
b. The FAA offers the streamlined conformity process as a preferred method for requesting conformity inspections. For this to work, the FAA and applicant must define:
(1) The most effective conformity notification process before the TC board meetings, and
(2) Criteria for determining certification branch, CM section, and designee involvement.
c. Expanded Use of the Conformity Plan.
(1) The most important component for a successful conformity notification is the up- front conformity plan. The conformity plan allows both the applicant and the FAA to coordinate conformity inspections better. The plan details areas where the certification branch, manufacturing specialist, and CM Section need to be involved. It also details when the FAA authorizes the applicant to use direct notification of conformity requirements. One expected benefit of using the conformity plan is that it helps identify when DERs should fill out FAA Form 8120-10 for parts or tests.
(2) If the applicant and certification branch previously agree, the applicant’s DER may fill out this form and the applicant’s properly authorized designated inspection representative may perform the conformity inspection without prior certification branch review. Also, in the plan, the certification branch will define those Form 8120-10s it will need to review before the conformity inspection. Finally, the CM section helps determine which conformity inspections are eligible for DERs to notify the properly authorized designated inspection representative.
(3) For a successful inspection, the applicant should address details of conformity delegation early in the certification project. The certification branch project manager should notify the applicant as soon as possible of the need for upfront planning and development of the conformity plan, ideally before the initial TC board meeting. The applicant must draft the plan and the certification branch and CM section representatives must accept it before issuing the first conformity request. Applicants also should know that if they do not ask to use the direct conformity notification process early in the program and do not do any upfront planning, they cannot use this process.
(4) In the early phase of the certification project, the applicant needs to identify a DER coordinator (not necessarily a DER) by name. The DER coordinator ensures efficient scheduling of the designated inspection representatives and serves as a focal point with the certification branch. Depending on scheduling and locations of the conformity inspections, the DER coordinator may identify the designated inspection representatives who will receive conformity requests. Based on criteria in subparagraph 5-5c(6) below, the FAA will approve specific DERs and designated inspection representatives for the process.
(5) The applicant needs to generate a matrix and schedule for conformity inspection requirements as part of the overall certification plan. At a minimum, the matrix should list:
(a) The proposed conformity activities,
Par 5-5 Page 109
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
FAA Order 8110.4C and FAA Order 8110.37G — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source