FAA Advisory circularActive

AC 20-184A

Guidance on Testing and Installation of Rechargeable Lithium Battery and Battery Systems on Aircraft

20-184A Source checked 2026-11-28

Scope, source and reading notes

Design, installation, operation, and maintenance of rechargeable lithium batteries and battery systems under applicable airworthiness requirements.

Aerospace Consulting reference note: Testing and installation guidance for rechargeable lithium battery systems on aircraft; revision A supersedes AC 20-184.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: f2402c97abdd38bf5569f097e8f24be48e024dbf4210e6fa551ada910dcc66a7

Source page 52 · PDF page 52

09/18/2026

Appendix G

compliance with § 23.2410 in conjunction with complying with the rechargeable lithium battery SOs. Clearly state the method of compliance in your response to this section of the AC.

G.7 Lithium Battery Installed in a Designated Fire Zone (DFZ) (§§ 23.244 0 and 23.2510).

G.7.1 Installation in a DFZ should be avoided, but may be acceptable if the battery location does not create an additional hazard. The external fire threat to the battery when it is located in a DFZ is a 2000°F flame for 15 minutes per AC 20-135, Powerplant Installation and Propulsion System Component Fire Protection Test Methods, Standards, and Criteria. The heat generated by this flame may cause multiple cells to enter thermal runaway along with damage to the battery containment system resulting in uncontrolled fire or explosion.

G.7.2 In accordance with § 23.2440(c)(1) and any other applicable airworthiness regulation references in table 2-1 of AC 20-184A, the battery must contain or vent any thermal runaway and pr event introduction of additional hazards when exposed to a 2000°F flame for 15 minutes. Test by exposing the battery installation design (including any vents) to a 2000°F flame for 15 minutes per AC 20-135. Ensure no additional hazards are introduced. For all batteries installed in a DFZ, minimize the risk of fire in the DFZ. Some examples are:

G.7.2.1 Directing and venting (if the design includes a vent) any potential flames or flammable material from the battery out of the fire zone. Any vent system included in the design must continue to function in the event of a thermal runaway of the battery, otherwise it must not create an additional hazard from its failure.

G.7.2.2 Using fireproof materials in the construction of the battery installation design.

G.7.2.3 Providing adequate shielding to protect the battery and vent, if any, from direct flames to ensure the battery remains below a temperature that could compromise the thermal runaway containment integrity when exposed to a powerplant fire condition.

G.8 Hazard Mitigations for Large Battery System Thermal Runaway Conditions. Airplanes requiring high-capacity batteries may increase the severity level and adverse effects resulting from a battery thermal runaway condition or any other hazards. Using RTCA DO-311A, including articles approved under TSO-C179b, is an accepted approach for addressing the thermal runaway aspects of rechargeable lithium battery installations. All applicable airworthiness regulations must be addressed and complied with. RTCA DO-311A, as well as TSO-C179b, provide a testing standard and article- level approval that requires additional integration and mitigation strategies in order to

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

25-887-SC

Related technical context

Engineering context
Evidence and scope

AC 20-184A and 25-887-SC — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.