AC 20-184A
Guidance on Testing and Installation of Rechargeable Lithium Battery and Battery Systems on Aircraft
20-184A Source checked 2026-11-28
Scope, source and reading notes
Design, installation, operation, and maintenance of rechargeable lithium batteries and battery systems under applicable airworthiness requirements.
Aerospace Consulting reference note: Testing and installation guidance for rechargeable lithium battery systems on aircraft; revision A supersedes AC 20-184.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: f2402c97abdd38bf5569f097e8f24be48e024dbf4210e6fa551ada910dcc66a7
09/18/2026
CHAPTER 3. MAINTENANCE AND OPERATIONAL CONSIDERATIONS FOR LITHIUM
BATTERY SYSTEMS
3.1 Introduction. Lithium batteries can be hazardous if not maintained a nd handled properly. This chapter provides guidance for maintenance considerations for aircraft lithium b atteries. Maintenance requirements are part of the ICA that must comply with § 21.50 and to the applicable 23.1529, 25.1529, 27.1529, 29.1529 sections. This AC has appendices that include further relevant references to assist in compliance (i.e. recording pertinent maintenance data to document the service life of the lithium battery and battery system to ensure the airworthiness of the battery system and aircraft).
3.2 Aircraft Battery Maintenance. Manufacturer procedures for maintenance should be followed because maintenance and inspection requirements for aircraft lithium batteries vary based on the type of chemical technology and physical construction of the battery. Performance of lithium batteries at any time in a given installation will depend on several factors that include but are not limited to the following (refer to 14 CFR § 43.1 3 for additional requirements):
3.2.1 Lithium Battery Chemistry. The electrolyte used in lithium batteries can be a highly reactive substance and care must be observed in maintaining the lithium batteries in accordance with both the OEM maintenance manual and the applicable regulations referenced in table 2-1.
3.2.2 Age Management. To determine the life and age of the installed lithium battery, record the installation date of the battery. During normal battery maintenance, document battery age in either the aircraft maintenance log or the shop maintenance log. Do not keep batteries in service longer than recommended by the manufacturer.
3.2.3 State of Charge. State of charge of the lithium battery is determined by the cumulative effect of charging and discharging the battery. In a normal electrical charging system, the generator or alternator restores a battery to full charge during a flight regardless of use before flight. However, safeguards must be implemented to ensure the aircraft does not begin flight with a battery not sufficiently charged to accomplish its intended function of continued safe flight and landing of the aircraft in accordance with the applicable regulations referenced in table 2-1. (See appendix E , Note 1, for the definition of “sufficiently charged”.)
3.2.4 State of Health. Determine the state of health of the lithium battery by r ecording various parameters including t he following:
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-184A and 25-887-SC — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source