Scope, source and reading notes

Design, installation, operation, and maintenance of rechargeable lithium batteries and battery systems under applicable airworthiness requirements.

Aerospace Consulting reference note: Testing and installation guidance for rechargeable lithium battery systems on aircraft; revision A supersedes AC 20-184.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: f2402c97abdd38bf5569f097e8f24be48e024dbf4210e6fa551ada910dcc66a7

Source page 47 · PDF page 47

09/18/2026

Appendix G

G.2.6 SO 6: Have provisions to prevent any hazardous effect on airplane structure or systems caused by the maximum amount of heat it can generate due to any failure of it or its individual cells.

G.2.7 SO 7: Have a failure sensing and warning system to alert the flightcrew if its failure affects safe operation of the airplane.

G.2.8 SO 8: Have a monitoring and warning feature that alerts the flightcrew when its charge state falls below acceptable levels if its function is required for safe operation of the airplane.

G.2.9 SO 9: Have a means to disconnect from its charging source in the event of an over- temperature condition, cell failure, or battery failure.

G.3 Method of Compliance with Safety Objectives.

G.3.1 RTCA DO-311A provides data used to demonstrate that rechargeable lithium battery installations meet the means of compliance SOs when using this AC for compliance.

G.3.2 RTCA DO-311A, s ection 2.1, General Requirements, provides design requirements and guidelines that are pertinent to designing safe batteries and meeting Part 23 requirements and the means of compliance SOs. Consider each of these requirements and guidelines when designing cells and batteries.

G.3.3 RTCA DO-311A, sections 1.4, 1.5, 1.6, a nd 2.1 provide guidelines and general requirements that are pertinent to designing and installing safe lithium batteries on aircraft.

G.3.4 SOs 1 and 2 are intended to ensure that the cells and battery are designed to eliminate the potential for uncontrollable failures. However, a certain number of failures will still occur due to various factors beyond the control of the designer. Therefore, the means of compliance SOs, as a whole, are intended to protect the airplane and its occupants if failure occurs.

G.3.5 The following method of compliance must be used to comply with the means of compliance in G.2 a bove. Means of compliance SOs are independent of each other. Demonstrating compliance with one of these SOs does not constitute compliance with the other SOs.

G.3.5.1 SO 1: Designed to maintain safe cell temperatures and pressures under all foreseeable operating conditions to prevent fire and explosion. Method of Compliance with SO 1:

1. Show that batteries meet the requirements in RTCA DO-311A, sections 2.2, Equipment Requirements – St andard Conditions (which are applicable according to section 2.4.2) and section 2.3, Equipment Requirements – E nvironmental Conditions.

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

25-887-SC

Related technical context

Engineering context
Evidence and scope

AC 20-184A and 25-887-SC — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.