Certification of Normal Category Rotorcraft — Changes 1–9
Normal category rotorcraft guidance with Changes 1–9 incorporated. Search the complete AC or start with the system safety, flight controls and instrument-flight guidance.
This source includes guidance for different amendments of Part 27. Match the guidance to the aircraft’s agreed certification basis: the 27.1309 entries for Amendments 27-21, 27-46 and 27-51 are separate. The base AC was issued on 30 September 1999; Change 9 is dated 23 June 2023. The FAA catalogue’s 30 September 2008 date is not the date of the latest change.
The source, within reach.
Search within this AC, jump to a source page, or download the complete saved publication.
This extraction supports search. Read the original page for complete notation and layout.
AC 27-1BChg 4 12/15/2009
(4) Lower load factors may be used only when justified by manufacturer’s data,
rational analysis, actual rotorcraft flight data and ground load demonstrations, or any
combination of these approaches.
(5) Tank pressure testing, while not mandated, is recommended for safety
reasons. An acceptable procedure is included in paragraph c.(4) under “Acceptable
Means of Compliance.”
(6) Dispensing equipment installation attach points that are an integral part of the
rotorcraft and have been certified to the appropriate airworthiness standards, need no
further substantiation. This applies provided a load analysis indicates the dispensing
system does not impose loads at the attach points which exceed those approved as
part of the rotorcraft certification.
(7) A 5-inch ground clearance for skid gear equipped, newly manufactured
rotorcraft has typically been used when installing dispensing equipment, such as belly
mounted supply tanks/hoppers or when installing dual side mounted supply
tanks/hoppers. This applies provided the rotorcraft design incorporates cross tubes or
other skid gear reinforcing structure below the fuselage and the cross tubes have not
experienced in-service permanent elastic deformation. For rotorcraft equipped with
wheels and/or landing gear struts, the maximum system deflections should be
considered when determining the 5 inches of acceptable static ground clearance. A
3-inch ground clearance has been found acceptable and may be approved for skid gear
equipped rotorcraft to account for the in-service permanent elastic deformation allowed
for skid gear members (i.e., cross tube deflections allowed per the maintenance
manual). Cable supported systems (e.g., cargo hook installations) or dispensing
systems utilizing flexible ducts, such as water snorkels, have been approved even
though portions of the systems contact the surface during a normal landing. A
determination should be made that these systems do not interfere with the safe landing
of the rotorcraft.
(8) A number of rotorcraft are approved for external cargo operations that allow a
gross weight higher than the approved internal gross weight limit. This difference is
usually due to the allowable weight limit restriction of the landing gear. (The gear is not
approved for the higher weight.) Those types of dispensing equipment, which can be
loaded in flight to a weight that exceeds the allowable limit of the landing gear, should
incorporate a reliable means that rapidly reduces the total aircraft gross weight to within
allowable landing gear limits. In most cases, this will involve jettison of the disposable
load. The time interval for this operation should be demonstrated, and should not
exceed a recommended 3 seconds from a level flight condition.
(9) A flight check or demonstration of the agricultural dispensing equipment
installation is normally conducted. This flight check should also qualitatively determine
that no hazardous deflection or resonance in the rotorcraft or dispensing system exists.
For FAA flight operations approval, this flight check must be conducted under the
requirements of § 133.41.
Page MG 5 - 4
Saved from the FAA on November 17, 2026. All original pages are retained. Engineering explanations are presented separately below.
Aerospace Consulting / Engineering perspective
Start with the certification basis and the function.
Identify the applicable amendment before selecting the safety guidance. Connect intended functions and operating conditions to failure conditions, architecture decisions, common-cause considerations, verification and limitations. For flight controls and IFR work, carry the relevant 27.672, 27.1329 and Appendix B assumptions into the system safety and compliance evidence.
1196 original pages. 0 pages have reviewed text reflows. Original-first pages retain the source layout, with extracted text available for finding words.
A focused review, an agreed assessment package or ongoing support alongside your team. We can agree the relevant inputs and scope in the initial conversation.
This opens your email application.
Start a conversation
Tell us about your programme, the system you are developing and the support you need.
We can agree a focused use-case review, a defined evidence package or ongoing programme support.
This opens your email application.
Specialist aerospace expertise
Aerospace Consulting is led by Hussein Khimji, an FAA Designated Engineering Representative in systems and equipment, with a focus on system safety, flight controls and avionics.
We work with aircraft developers and systems suppliers to connect technical decisions, safety assessments and certification evidence.
This is the proposed introduction. The full About page will add your approved biography and associate expertise.
Systems engineering & development assurance
Tell us about the aircraft or system, its intended function, stage of development and the support you need.