EASA Certification Specifications with AMC/GMFinal — current published edition checked

CS-29

Large Rotorcraft

Amendment 12 Source checked 2026-11-28

Scope, source and reading notes

Complete Easy Access Rules consolidation of CS-29 Amendment 12.

Aerospace Consulting reference note: Certification specifications and related compliance guidance for large rotorcraft, including the Amendment 12 vibration health monitoring provisions.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 37c3d4af295ea3ec222370e326c63753dabcbf00735cf671f3ad86e9d46cba66

Source page 439 · PDF page 439

For drive system gearboxes that are essential to drive the rotors, EASA considers that the initial TBO at EIS and the plan to increase it in service should be justified. For this purpose, the following should be considered by the applicant:

— Initial TBO (applicable at EIS)

At EIS, the available data supporting the justification of the TBO of a rotor drive system gearbox is typically limited. The applicant should, therefore, propose a conservative initial TBO supported by the data coming from:

the endurance test,

flight tests,

other relevant tests, and

experience on similar design having the same characteristics.

The applicant should take into account that, in general, only limited experience of the real operating environment and conditions for a new gearbox is available at EIS.

This initial TBO should ensure enough opportunities to verify the condition of internal gearbox components in order to validate the assumptions made at the time of certification, preventing that any compromised assumption may lead to an in-service catastrophic or hazardous failure.

— TBO step increase

The increase of a gearbox TBO in service should be accomplished in steps providing confidence progressively in the validity of the certification assumptions. Each TBO step increase should:

— only be proposed when the current TBO is supported by a sufficient number of gearbox overhaul inspection results;

— be based on a sufficient number of gearboxes from the fleet to be inspected, and take into account the representativeness of operational and environmental aspects of the selected samples to represent the full spectrum of gearbox usage;

— be based on technical justifications from overhauled gearboxes (e.g. condition of inspected parts, evidence from similar designs, etc.), maturity testing and in-service feedback (incidents, health and usage monitoring system (HUMS) data, etc.); and

— be completed prior to formally increasing the TBO to verify acceptable behaviour and condition of the gearbox components prior to starting a new increase phase.

— Management of TBO steps

The process for managing the evolution of the TBO of drive system gearboxes should be documented in a TBO maturity plan. This should include:

— planned increase steps and target TBO, technical criteria for the validation of the steps planned and justification of the proposed plan (see note 1);

— definition of the number of gearboxes and selection criteria considering operation and environment (see note 1);

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 29-2C

Related technical context

Engineering context
Evidence and scope

CS-29 and AC 29-2C — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.