Scope, source and reading notes
This source includes guidance for different amendments of Part 27. Match the guidance to the aircraft’s agreed certification basis: the 27.1309 entries for Amendments 27-21, 27-46 and 27-51 are separate. The base AC was issued on 30 September 1999; Change 9 is dated 23 June 2023. The FAA catalogue’s 30 September 2008 date is not the date of the latest change.
Aerospace Consulting reference note: Complete normal-category rotorcraft guidance, including system safety, equipment, flight guidance and IFR certification.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 2dfac16a3644dc18997069cca78746c10726e4b70d3aba996fc87843ffe68a2b
vii. MOC for Objective 9: Objective 9 specifies flight crew alerting if the failure of a battery installation, in itself or in relation to a system that performs an aircraft-level function, could result in “unsafe system operating conditions.” The alert should comply with the applicable color requirements in § 27.1322. The applicant should refer to Section AC 27.1322 for an acceptable method of compliance.
viii. MOC for Objective 10: The following are examples of “means” for flight crew or maintenance personnel to determine the battery charge state:
(a) A manually activated system (e.g., push button) that displays the available charge of each battery unit.
(b) An automatic system that records the available charge of each battery unit on an appropriate interval and makes it available to maintenance personnel before the next flight.
(c) Physical access that allows a maintenance person to measure the battery charge state.
3. The MOCs for Objectives 1 through 10 are only acceptable for required functions if ICAs include a check of the battery charge state within an interval that will ensure sufficient charge for each flight considering the worst case scenario and replacement of the battery when the charge is not sufficient.
4. MOC for Very Small Non-Rechargeable Lithium Batteries:
An acceptable MOC for Objectives 1 through 8 for non-rechargeable lithium battery installations that have less than 2 watt-hours of energy is showing these batteries meet Underwriters Laboratories (UL) 1642 or UL 2054.
(ix) Part 27 Compliance. Non-rechargeable lithium battery installations should satisfy each of the MOCs identified in this guidance to comply with all applicable part 27 requirements. The following provides means of compliance and other information on some part 27 requirements:
(A) System Safety Assessment. Although these hazard conditions require specific functionalities and capabilities and address certain critical failure modes of non- rechargeable lithium batteries and their installations, the applicant must also meet the requirements of § § 27.1301 and 27.1309. To date, in-service experience has shown that non-rechargeable lithium battery thermal/pressure runaway conditions are not extremely improbable. Assume such failures could occur sometime during the life of the battery installation when demonstrating compliance with § 27.1309. Application of
View figures, tables and original page layout

Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 27-1B and AC 29-2C — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting sourceRelated technical context
Engineering contextEvidence and scope
CS-27 and AC 27-1B — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source