Certification of Normal Category Rotorcraft — Changes 1–9
Normal category rotorcraft guidance with Changes 1–9 incorporated. Search the complete AC or start with the system safety, flight controls and instrument-flight guidance.
This source includes guidance for different amendments of Part 27. Match the guidance to the aircraft’s agreed certification basis: the 27.1309 entries for Amendments 27-21, 27-46 and 27-51 are separate. The base AC was issued on 30 September 1999; Change 9 is dated 23 June 2023. The FAA catalogue’s 30 September 2008 date is not the date of the latest change.
The source, within reach.
Search within this AC, jump to a source page, or download the complete saved publication.
This extraction supports search. Read the original page for complete notation and layout.
AC 27-1B, Chg 7 2/4/2016
(ii) Identify the operations the system is designed to support. Although sometimes
considered less complex than installations for operation under IFR, the HF evaluation of installations for
operation under VFR should include the same rigor, as both present HF challenges to the pilot. For
example, complex systems or systems that require the pilot to spend considerable time interfacing with a
system’s functions and interactions with other rotorcraft systems will require the pilot to allocate attention
from flying the rotorcraft. The results are increased workload with varying changes in the pilot’s ability to
attend to flying the rotorcraft. The following are some considerations:
(A) For rotorcraft operating only under VFR, describe the operations the system is meant
to support, taking into account day and night operations. For example, for installation of an electronic
display systems (EDS) display suite that integrates with external GPS navigators, consider:
(1) The effect of the pilot-system interface on the pilot’s attention allocation and
workload.
(2) How it affects the pilot’s external scan and “see and avoid” tasks (whether it
requires extensive heads-down time).
(B) For rotorcraft certificated to operate under IFR, describe the operations the system
supports. For example, for installation of a new EDS suite and a WAAS GPS system that interfaces with
the existing autopilot and one of the new operations is steep angle low speed approaches, consider how
the system will support or change pilot workload.
(iii) System Operation procedures. Describe and evaluate the pilot procedures for both
normal and abnormal conditions since the design of the system and use of procedures are interrelated.
Additionally, development and presentation of procedures and limitations can affect pilot workload,
particularly in abnormal conditions. Identify and evaluate any expected pilot memory or “bold-face” items
(procedures that the pilot must perform from memory prior to referencing a checklist or flight manual). In
addition to the flight manual or flight manual supplement, system operations procedures may include:
(A) Quick reference handbook to accompany the flight manual.
(B) Abbreviated checklists to accompany the flight manual.
e. Certification Requirements. Identify the regulations in the certification basis for system or
component installations that have HF implications. These can be identified either as part of the
certification plan or a separate human factors certification plan. The certification plan should indicate the
method of compliance for each regulation and contain sufficient detail to ensure human factors
considerations are adequately addressed. The plan should also allow adequate time to accomplish all
necessary testing agreed to by the applicant and the FAA.
(1) Address and evaluate the following in the certification plan:
(i) The intended use of the system does not require any exceptional skill or generate any
unreasonable workload for the pilot.
(ii) The use of the display does not require unreasonable training requirements to
demonstrate adequately that the pilot can understand and properly operate the system in all operational
environments.
(iii) Demonstration of the design characteristics of the display system support error avoidance
and management (e.g., detection, recovery, etc.).
(iv) The display system integration is consistent or compatible with other cockpit controls and
creates no added burden on the pilot with respect to the new display system or operation of other
systems.
Page MG 20 -8
Saved from the FAA on November 17, 2026. All original pages are retained. Engineering explanations are presented separately below.
Aerospace Consulting / Engineering perspective
Start with the certification basis and the function.
Identify the applicable amendment before selecting the safety guidance. Connect intended functions and operating conditions to failure conditions, architecture decisions, common-cause considerations, verification and limitations. For flight controls and IFR work, carry the relevant 27.672, 27.1329 and Appendix B assumptions into the system safety and compliance evidence.
1196 original pages. 0 pages have reviewed text reflows. Original-first pages retain the source layout, with extracted text available for finding words.
A focused review, an agreed assessment package or ongoing support alongside your team. We can agree the relevant inputs and scope in the initial conversation.
This opens your email application.
Start a conversation
Tell us about your programme, the system you are developing and the support you need.
We can agree a focused use-case review, a defined evidence package or ongoing programme support.
This opens your email application.
Specialist aerospace expertise
Aerospace Consulting is led by Hussein Khimji, an FAA Designated Engineering Representative in systems and equipment, with a focus on system safety, flight controls and avionics.
We work with aircraft developers and systems suppliers to connect technical decisions, safety assessments and certification evidence.
This is the proposed introduction. The full About page will add your approved biography and associate expertise.
Systems engineering & development assurance
Tell us about the aircraft or system, its intended function, stage of development and the support you need.