Aircraft electrical and electronic system lightning protection for applicable Part 23, 25, 27, and 29 certification requirements.

Aerospace Consulting reference note: Describes a means of demonstrating lightning-protection compliance for aircraft systems; revision C supersedes AC 20-136B.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: a97137a34f9094ac10e6fb7caba11688edf5ab0b866ddf3d5ffa40f00e327cdd

Source page 33 · PDF page 33

10.12 Step 12 – Verify Compliance with the Requirements. You should compare the verified system ETDLs with the aircraft ATLs and determine if an acceptable margin exists between the ETDLs and ATLs. Margins account for uncertainty in the verification method. As confidence in the verification method increases, the margin can decrease. An ETDL exceeding the ATL by a factor of two is an acceptable margin for LCL A systems if this margin is verified by aircraft test or by analysis supported by aircraft tests. For LCL A display systems where the ETDLs are determined using guidance provided in Table 4, an acceptable margin is already incorporated in the selected ETDLs. For other verification methods, the margin should be agreed upon with the cognizant certification branch.

10.13 Step 13 – Take Corrective Measures.

10.13.1 When your system fails to meet the certification requirements, corrective actions should be selected. The changes or modifications you make to the aircraft, system installation or the equipment may require more testing and analysis.

10.13.2 To meet the certification requirements, you may need to repeat system qualification testing, or aircraft testing and analysis (in whole or in part). You also may need to modify the system or installation to get certification. You should review these changes or modifications with the cognizant certification branch to determine if they are significant. If these changes or modifications are significant, update your lightning certification plan accordingly. The updated certification plan should be resubmitted to the certification branch for review.

10.14 Compliance for LCL A Systems on Level 1, 2, 3, and 4 Airplanes Certified Under Part 23.

10.14.1 Airplane certification levels 1, 2, 3, and 4 are defined in § 23.2005 (established by amendment 23-64). Airplane certification classes I, II, III, and IV are defined in AC 23.1309-1.

10.14.2 The following test levels may be used for LCL A integrated systems on normal category level 1, 2, 3, and 4 airplanes (certification class I, II, III, and IV). Equipment testing may be acceptable if you show that equipment in the LCL A systems can be operated and tested independently, as well as can be effectively monitored to verify no adverse effects to the system and function. Otherwise, you should perform integrated system lightning tests as discussed in step 5 (refer to paragraph 10.5). The system should comprise all equipment and wiring needed to perform the function. One or more of these systems with redundant channels may perform the same function. When there are multiple systems with redundant channels performing the same function, it is only necessary for one of the multiple systems’ redundant channels to meet the requirements in § 23.1306(a) (amendment 23-61) or § 23.2515(a).

10.14.3 Level 1 airplanes certificated under part 23 meet the same requirements for lightning compliance as shown in paragraph 10.14.5 below. Level 2 and 3 airplanes certificated under part 23 meet the requirements for lightning as shown in paragraph 10.14.6 below.

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AMC 20-136A

Related technical context

Engineering context
Evidence and scope

AC 20-136C and AMC 20-136A — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.