EASA Means of ComplianceFinal — current published edition checked

MOC-5 SC-VTOL

Means of Compliance with SC-VTOL — Batch 5

Issue 2 — FINAL Source checked 2026-11-28

Scope, source and reading notes

Complete final batch 5 of SC-VTOL means of compliance. Later batches may amend individual provisions in earlier batches.

Aerospace Consulting reference note: Fifth final batch, introducing additional means of compliance and amendments to earlier MoC batches. This is the final Issue 2, not the consultation draft or tracked copy.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 5e91110d91378ed3836aafe2cb30871f5b2d3802a92b97a28acf42913467a949

Source page 23 · PDF page 23

Doc. No: MOC-5 SC-VTOL Issue: 2 Date: 5 November 2026

Special Condition VTOL

simultaneous failures of all affected equipment. Therefore, it should not be assumed that IDAL A items are protected from such development errors and consequently they should be included in the scope of the common mode analysis irrespective of the FDAL/IDAL of the system/item.

The following structured approach described in Appendix M of ED-135/ARP4761A is accepted to accomplish a common mode analysis:

(1) Establish project specific CMA questionnaires (identifying common cause types and potential

common cause sources and common failures, which could affect the independence). ED- 135/ARP4761A paragraph M.3.1 and table M-1 can be followed for this purpose. ED-334 provides some VTOL specific guidance that can be used to tailor CMA questionnaires. These should be used to identify independence shortcomings, define, evaluate, and verify independence principles and independence requirements

(2) Identify the independence principles and requirements for the aircraft, system and item level. ED-

135/ARP4761A paragraph M.3.2.2, B.4.3.3, D.4.2.2 and D.4.3.1 can be followed for this purpose.

Independence principles are identified either by design analysis and how it relates to the Failure Conditions or safety requirements identified in the safety assessment; or by examination of the safety analyses (e.g. fault-tree AND-gates, or minimal cut sets, of Failure Conditions). These Failure Conditions should cover both the availability (i.e. loss) and integrity of functions and protections.

(3) Examine the implementation to verify that the independence principles and requirements have

been accomplished. ED-135/ARP4761A paragraph M.3.2.2 and M.3.3.2 can be followed for this purpose.

The analysis of the implementation:

(i) should be conducted at aircraft, system, equipment and item level (considering all hardware

and software elements composing a defined Airborne Electronic Hardware item or Software item), and

(ii) should address both the availability (i.e. loss) and integrity of functions and protections.

(4) Document the results of the above steps of the CMA process. ED-135/ARP4761A paragraph

M.3.2.1.4 , M.3.2.2.4, M.3.3.1.4 and M.3.3.2.4 can be followed for this purpose.

Additional considerations may be appropriate for some specific systems and functions. In particular for Fly-by- wire Flight Control Functions, MOC 4 VTOL.2300 applies.

Note:

Section 10. Development Assurance Process. The following changes are introduced. Unchanged text is not reproduced for clarity. Changes are highlighted in blue colour for reader’s convenience.

(a) Development Assurance Level (DAL) allocation

[…]

View figures, tables and original page layoutOriginal source page Source page 23 · PDF page 23 of MOC-5 SC-VTOL

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

SC-VTOL-02

Related technical context

Engineering context
Evidence and scope

SC-VTOL-02 and MOC-5 SC-VTOL — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.