EASA Certification Specifications with AMC/GMFinal — current published edition checked

CS-27

Small Rotorcraft

Amendment 10; corrected 15 September 2025 Source checked 2026-11-28

Scope, source and reading notes

Complete official CS-27 Amendment 10, including AMC, GM and appendices.

Aerospace Consulting reference note: Certification specifications and related compliance guidance for small rotorcraft, using the corrected official publication.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: e762c494818f5badf2cceb0a8dc04e8cf5938efa2552deeadc0f708d1ead92ae

Source page 80 · PDF page 80

CS 27.610 requires the protection of rotorcraft structural components, propulsion system, gearboxes, mechanical and hydraulic control systems from lightning effects that could result in catastrophic failures.

However, damage, failure or departure of any rotorcraft component which could endanger the rotorcraft or its occupants should be part of the evaluation.

This AMC provides detailed guidance on damage tolerance evaluation, including residual strength criteria after lightning strike to ensure continuous safe flight and landing.

Each part, the failure of which implies potential catastrophic consequences and that is exposed to damage under lightning conditions, should be subject to further evaluation which includes:

(1) the nature and extent of the lightning damage (threat assessment, damage detectability, etc.);

(2) the demonstration of the functionality of the affected part up to detection;

(3) a static residual strength capability demonstration supported by analysis and/or test;

(4) when found necessary, a fatigue evaluation of a part with lightning damage for the demonstration of the exposure time before detection.

The airworthiness instruction requested after lightning strike (flight manual and maintenance instructions, etc.) should be consistent with the functional, static and fatigue evaluation of the damage consequences (considered to be a partial failure).

A similar approach should be considered for non-metallic components (for composite, see the AMC 20-29 (11c) guidance).

The above approach is also considered to be applicable for parts departure which could preclude continued safe flight and landing.

For non-structural components (e.g. radomes, panels), only static residual strength is requested for part detachment which could preclude continued safe flight and landing.

[Amdt 27/10]

CS 27.611 Inspection provisions

There must be means to allow the close examination of each part that requires:

(a) Recurring inspection;

(b) Adjustment for proper alignment and functioning; or

(c) Lubrication.

CS 27.613 Material strength properties and design values

(a) Material strength properties must be based on enough tests of material meeting specifications to establish design values on a statistical basis.

(b) Design values must be chosen to minimise the probability of structural failure due to material variability. Except as provided in sub-paragraphs (d) and (e), compliance with this paragraph must be shown by selecting design values that assure material strength with the following probability:

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 27-1B

Related technical context

Engineering context
Evidence and scope

CS-27 and AC 27-1B — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.