Scope, source and reading notes
Transport category rotorcraft certification guidance under Part 29; consolidated FAA publication incorporating Changes 1 through 9. Base publication catalog date: 2008-09-30; latest included change: 2023-06-23.
Aerospace Consulting reference note: Broad Part 29 guidance covering transport rotorcraft design, flight, equipment, systems, and certification, including system safety and flight guidance.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: c57691386dd1e59263633bd8fdaabb842a958061a9b6a82d30dad18358977013
(i) The fuel be supplied within the appropriate engine fuel pressure range;
(ii) The test be conducted with minimum fuel onboard, consistent with test safety;
(iii) For pump systems, fuel flow requirements be satisfied with the critical airframe furnished pump inoperative; and
(iv) The fuel flowmeter, if installed, must be blocked such that fuel must flow through the meter or its bypass.
(3) Section 29.955(b) specifies that if an engine can be supplied with fuel from more than one tank, the fuel system must feed promptly when fuel becomes low in one tank and another tank is selected.
b. Procedures.
(1) Testing (including bench tests) has been the accepted method to show compliance with § 29.955(a). Analytical techniques may be used to adjust the system test results to various fuel conditions and flows or to account for minor modifications to a system. A purely analytical approach is not generally acceptable.
(i) Methods to adjust the test data for different fuel properties and flows should be verified by limited testing.
(ii) If a suction lift system is used and hot fuel verification is involved (reference § 29.961) testing is appropriate.
(2) Demonstrating that the system is capable of providing “…100 percent of the fuel flow required under the intended operating conditions…” will depend on the particular system design, whether boosted or suction lift, Category A or Category B, and whether single or multiengine. Some of the factors to be evaluated are as follows:
(i) Acceleration fuel flow requirements may exceed those for steady-state operation. For example, if on a cold day, engine torque is the limiting parameter, the steady-state fuel flow demand corresponding to that torque may be exceeded during engine acceleration to that power.
(ii) For single-engine rotorcraft and for multiengine rotorcraft with all engines operating, some margin should be included to account for possible inadvertent overtorque.
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 27-1B and AC 29-2C — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting sourceRelated technical context
Engineering contextEvidence and scope
CS-29 and AC 29-2C — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source