FAA Advisory circularActive

AC 20-158B

The Certification of Aircraft Electrical and Electronic Systems for Operation in the High-Intensity Radiated Fields (HIRF) Environment

20-158B Source checked 2026-11-28

Scope, source and reading notes

HIRF protection for aircraft electrical and electronic systems where the certification basis includes the specified Part 23, 25, 27, or 29 requirements.

Aerospace Consulting reference note: Guidance for demonstrating that aircraft electrical and electronic systems are protected against the high-intensity radiated fields environment.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: c3be1c8b9e84592a978a2be6c3b8f89abfa59a6430af80afdacee892c3c917d3

Source page 22 · PDF page 22

9.2 HIRF Verification Test, Analysis, or Similarity Plan.

Test, analysis, and similarity are all acceptable methods for showing HIRF compliance. The applicant should choose the method most appropriate for its project. See paragraphs 10 and 11 of this AC and SAE ARP5583A, for additional guidance on selecting the appropriate method. Specific HIRF test, analysis, or similarity plans should be prepared to describe specific verification activities. One or more verification plans may be necessary. For example, there may be several systems or equipment laboratory test plans, an aircraft test plan, or a similarity plan for selected systems on an aircraft.

9.2.1 HIRF Test Plan.

A HIRF compliance test plan should include the equipment, system, and aircraft test objectives for the acquisition of data to support HIRF compliance verification. The test plan should provide an overview of the factors being addressed for each system test requirement. The test plan should describe the appropriate aspects of the systems to be tested and their installation. Additionally, the test plan should reflect the results of any analysis performed in the overall process of the HIRF compliance evaluation. The test plan should include:

• Purpose of the test;

• Description of the aircraft and/or system being tested;

• System configuration drawings;

• Proposed test setup and methods;

• Intended test levels, modulations, and frequency bands;

• Pass/fail criteria; and

• Test schedule and test location.

The test plan should cover HCL A, B, and C systems and equipment, as appropriate. HCL A systems may need both laboratory integrated systems tests and aircraft tests. HCL B and C systems and equipment need only equipment laboratory testing.

9.2.2 Analysis Plan.

A HIRF compliance analysis plan should include the objectives, both at the system and equipment level, for generating data to support HIRF compliance verification. Comprehensive modeling and analysis for RF field coupling to aircraft systems and structures is an emerging technology; therefore, the analysis plan should be coordinated with the FAA to determine an acceptable scope for the analysis. The analysis plan should include:

• Purpose and scope of the analysis;

• Description of the aircraft and/or system addressed by the analysis;

• System configuration descriptions;

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AMC 20-158A

Related technical context

Engineering context
Evidence and scope

AC 20-158B and AMC 20-158A — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.