AC 20-152A
Development Assurance for Airborne Electronic Hardware
20-152A · 2022-10-07 Source checked 2026-11-28
Scope, source and reading notes
Electronic hardware for type certification or TSO authorisation; objective applicability depends on the hardware and DAL.
Aerospace Consulting reference note: Hardware development assurance, including custom devices, commercial off-the-shelf devices and use of DO-254/ED-80.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 06b17bec98562261063d87e518df3fe581412a5dce64b39ef4769c57433b6bc6
gaps in the tool assessment and qualification process, for example, to explain the method of independent assessment of the tool output. In this case, a relevant tool history is considered to be complementary data, providing more assurance for a tool.
In addition to what is already referenced in ED-80/DO-254, Figure 11-1, Item 9, for tool qualification guidance, ED-12C/DO-178C and ED-215/DO-330 may also be used.
5.9 Clarifications to ED-80/DO-254 regarding Previously Developed Hardware
Previously developed hardware (PDH) is defined as a custom-developed hardware device that has been installed in an airborne system or equipment either approved through FAA type certification (TC/STC) or authorized through TSOA. The section providing clarification on the use of PDH also covers PDH that was developed and approved prior to the use of ED-80/DO-254 in civil certification.
This section provides guidance on the use of ED-80/DO-254, Section 11.1, for PDH.
Objective CD-12 When an applicant proposes to reuse PDH, the applicant should use ED-80/DO-254, Section 11.1 and its subordinate paragraphs. The applicant should perform the assessments and analyses required in ED-80/DO-254, Section 11.1, in order to ensure that using the PDH is valid and that the compliance shown during the previous approval was not compromised by any of the following:
1. Modification of the PDH for the new application or for obsolescence management;
2. Change to the function, change to its use, or change to a higher failure condition classification of the PDH in the new application; or
3. Change to the design environment of the PDH.
The results should be documented in the PHAC or any other appropriate planning document.
In the context of custom device development, any one of these three points potentially invalidates the original development assurance credit for the PDH. In case of change or modification, the applicant should assess these changes using ED-80/DO-254, Section 11.1 and its subordinate paragraphs. When the original design assurance of the PDH is invalidated by one of the above points, the custom device should be upgraded based on the assessment per ED-80/DO-254, Section 11.1. When upgrading the hardware, the applicant should consider the objectives of this document that are applicable per the assessment.
5.10 Clarifications to ED-80/DO-254, Appendix A
This section clarifies the life cycle data referenced in ED-80/DO-254, Appendix A as follows.
• The row corresponding to 10.1.6 “Hardware Process Assurance Plan” in Table A-1 should also indicate HC2 for Level C to be consistent with row 10.8.
View figures, tables and original page layout

Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related EASA guidance
Engineering contextEvidence and scope
AMC 20-152A §8(b)(1); AC 20-152A §8.3
The AMC cites AC 20-152 without a suffix; the AC cites AMC 20-152(). Pairing these selected editions is editorial.
Comparable subject; no claim of blanket equivalence or automatic mutual acceptance.
Supporting sourceRecognises this edition
Source-backedEvidence and scope
AC 20-152A §1, printed p1
Names ED-80, April 2000.
AEH; conditions in AC sections 1 and 2.
Supporting sourceRecognises this edition
Source-backedEvidence and scope
AC 20-152A §1, printed p1
Names DO-254, 19 April 2000.
AEH; conditions in AC sections 1 and 2.
Supporting sourceLists related requirement
Source-backedEvidence and scope
AC 20-152A §8.1, printed p25
Explicitly lists 25.1309 for AEH development assurance.
The source cites the section identifier, without a certification-basis amendment.
Supporting sourceReferenced by system-safety guidance
Source-backedEvidence and scope
AC 25.1309-1B §5.3.4.2, printed p5-4 / PDF p30
Identifies AC 20-152A as hardware development-assurance guidance.
Read the source scope and applicable project basis.
Supporting sourceReferences this edition
Source-backedEvidence and scope
AC 20-152A §8.4, printed p26
Lists ARP4754A with an explicit date.
Related material; not a replacement for hardware-specific guidance.
Supporting sourceReferences this edition
Source-backedEvidence and scope
AC 20-152A §8.4, printed p26
Lists ARP4761 with an explicit date.
Related material; not a replacement for hardware-specific guidance.
Supporting source