Complete final batch 4 of SC-VTOL means of compliance. Later batches may amend individual provisions in earlier batches.

Aerospace Consulting reference note: Fourth final batch, introducing further means of compliance and amendments to previous MoC publications.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: d66389491b058ad129efdb1faa6d7d29a1a2bc2bf70dda5612bd6b3f53e2d321

Source page 35 · PDF page 35

Doc. No: MOC-4 SC-VTOL Issue: 2 Date: 11 July 2025

Fourth Publication of Means of Compliance with the Special Condition VTOL

(f) The applicant should use the guidance introduced in MOC VTOL.2510 “Equipment, Systems, and Installations” to capture and manage FGS design needs identified from the safety assessment. (g) For Category Enhanced, the applicant should identify portions and equipment of the FGS whose failure may contribute to hazardous or catastrophic consequences, and which are thus subject to the in-service monitoring process, in order to support the showing of compliance with VTOL.2510 (c).

Explanatory Note:

The safety assessment is covered on a general basis by MOC VTOL.2510, referenced in section 7 of this MOC. The objective of this section is to remind some points and highlight specificities related to the FGS, aiming to ensure that applicants will consider these key aspects.

The validation aspects of the failure conditions are addressed in section 18 of this MOC.

13. Integration

The potential complexity of the FGS organisational, functional, and physical integration may have a bearing on the aircraft safety, by introducing higher risks of development errors, or combined failures affecting several (sub)functions and (sub)systems at a time.

(a) The applicant should clearly establish, describe, and assure the following:

roles and responsibilities of the stakeholders (e.g., applicant and their different teams, suppliers); detailed functional and physical integration; detailed interfaces within the FGS and with dependent systems; requirement and assumption management, within the FGS, with dependent systems, with all stakeholders, from aircraft level to system, software, and hardware levels.

(b) The applicant should carefully address the integration and interaction with the FCS and the lift/thrust system, whether direct or indirect. This may include –but not be limited to– the implementation of the FGS inner loops in flight control computers and the blending in the control laws, the mechanical interface between an FGS actuator and pilot control inceptors, the interactions between the FGS envelope protection and other protections, the effect of pilot trimming control, the effect of pilot control on an axis not covered by the FGS, the effect of the stability augmentation systems and of their loss, the effect of normal and degraded control laws, the effect of surface/lift/thrust actuation normal and degraded conditions, the effect of different lift/drag configurations.

(c) The applicant should carefully address the interface with sensors and sources (e.g., control panel, air data, inertial data, ground navaids, GNSS, FMS, or even the FGS outer loops for the FGS inner loops). This may include –but not be limited to– redundant signal management and source selection, mode reversion in case of failure, closing the loop on steering orders, ensuring compatible resolutions, frequencies, rates, and limits.

(d) When performing the safety assessment, the applicant should give specific attention to failures having combined effects on the FGS and other systems introduced by the integrated architecture. The applicant should perform a bottom-up safety analysis (e.g., system functional Failure Modes and Effect Analysis (FMEA)), addressing failure modes within the FGS but also from the dependent systems, addressing not only single failures but also relevant combinations of failure modes, and including consideration of cascading effects.

View figures, tables and original page layoutOriginal source page Source page 35 · PDF page 35 of MOC-4 SC-VTOL

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

SC-VTOL-02

Related technical context

Engineering context
Evidence and scope

SC-VTOL-02 and MOC-4 SC-VTOL — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.