AMC 20-189
The Management of Open Problem Reports (OPRs)
Current AMC; incorporated in AMC-20 Amendment 23 Source checked 2026-11-28
Scope, source and reading notes
Management and assessment of open problem reports; includes GM1, GM2 and GM3.
Aerospace Consulting reference note: Explains the evaluation, classification and disposition of open problem reports in the certification process.
Complete selected AMC and associated material, from PDF pages 583–591 of the AMC-20 consolidation. The original PDF contains the whole consolidation. Reading text is extracted; original figures and layout remain available.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b3d02d6ad4cd2833f79be85634221f52ea8bd90a84c733257193e4a60a2d536a
5.4 For PRs that may have an impact on other products or articles that are developed within an organisation, a means should be established for sharing PR information so that any necessary corrective actions can be taken.
6. OPR MANAGEMENT
An OPR management process, based on the PR management process, should be established across the system, software and AEH domains, including the following process steps:
6.1 The classification of OPRs
6.1.1 The applicant should establish an OPR classification scheme including, at a minimum, the
following classifications: ‘Significant’, ‘Functional’, ‘Process’ and ‘Life-cycle data’. Other classifications or subclassifications may be created as needed. The classification scheme should be described in the appropriate planning document(s).
6.1.2 Each OPR should be assigned a single classification per the classification scheme. When multiple
classifications apply, the OPR should be assigned the classification with the highest priority. The priority from highest to lowest (including the defined subclassifications) is:
1. ‘Significant’;
2. ‘Functional’;
3. ‘Process’;
4. ‘Life-cycle data’;
5. any other OPR classification.
Note: The classification of an individual OPR may differ from one stakeholder to another, depending on the known mitigations at the time of classification.
6.1.3 The classification of an OPR should account for and document all the mitigations known at the
time of classification that are under the control of the classifying stakeholder. A mitigation that is controlled by another stakeholder may be considered in the classification only if validated with that stakeholder, and provided this mitigation remains acceptable in the frame of the type certificate (TC) / supplemental type certificate (STC) approval or European technical standard order (ETSO) article authorisation, as applicable.
6.1.4 A stakeholder, other than the aircraft TC or STC applicant, should classify as ‘Significant’ any
OPR for which the classification may vary between ‘Functional’ and ‘Significant’, depending on the installation.
6.2 The assessment of OPRs
Each OPR should be assessed to determine:
1. any resulting functional limitations or operational restrictions at the equipment level (for ETSOs) or at the product level (for other types of approvals);
2. relationships that may exist with other OPRs; and
3. for a ‘Significant’ or ‘Functional’ OPR, the underlying technical cause of the problem.
6.3 Disposition: OPRs classified as ‘Significant’ per the classification in Section 6.1, for which no sufficient mitigation or justification exists to substantiate the acceptability of the safety effect, should be resolved prior to approval. The disposition of OPRs may involve coordination with the certification authority.
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-189 and AMC 20-189 — published scope