AC 20-189
Management of Open Problem Reports (OPRs)
20-189 Source checked 2026-11-28
Scope, source and reading notes
Management of open problem reports in the system, software, and airborne electronic hardware domains for type certification and TSO authorization.
Aerospace Consulting reference note: Provides a framework for assessing and managing unresolved problem reports and communicating their effects on certification findings.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 30042e1dfff49db2953e6683874baafdb912a9096900f3f62f3bb98ab3ba0b73
the safety effect, should be resolved prior to approval. The disposition of OPRs may involve coordination with the certification authority.
6.4 Reporting: An OPR summary report should be prepared and provided to the affected stakeholder(s), and to the certification authority upon request. The OPR summary report may be an aggregation of summaries (e.g., Software/Hardware Accomplishment Summaries or system-level OPR reports) prepared by all involved stakeholders. The summary report should provide access to the following information for each OPR:
6.4.1 Identification of the OPR (for example, the OPR ID);
6.4.2 Identification of the affected configuration item(s) (for example, the item part number, component name, artifact name) or of the affected process(es);
6.4.3 The title or a summary of the problem, formulated in a manner understandable by the affected stakeholder(s);
6.4.4 Description of the problem, formulated in a manner understandable by the affected stakeholder(s);
6.4.5 Conditions under which the problem occurs;
6.4.6 OPR classification and assessment results (per paragraphs 6.1 and 6.2), including:
6.4.6.1. For each OPR, regardless of its classification:
6.4.6.1.1. The classification of the OPR; and
6.4.6.1.2. Relationships that are known to exist with other OPRs.
6.4.6.2. For OPRs classified as ‘Significant’:
6.4.6.2.1. Description of any mitigations or justifications used to substantiate the acceptability of the OPR safety effect (per paragraph 6.3); and
6.4.6.2.2. Functional limitations and operational restrictions, if any.
6.4.6.3. For OPRs classified as ‘Functional’:
6.4.6.3.1. Description of any mitigations or justifications used to reduce the safety effect to Minor or No Safety Effect; and
6.4.6.3.2. Functional limitations and operational restrictions, if any.
6.4.6.4. For OPRs classified as ‘Process’, a description of the extent or nature of the process non-compliance or deficiency that might contribute to not satisfying the applicable development assurance objectives.
6.4.6.5. For each OPR not classified as ‘Significant’ or ‘Functional’, justification that the error cannot have a safety or functional effect.
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-189 and AMC 20-189 — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source