AC 20-189
Management of Open Problem Reports (OPRs)
20-189 Source checked 2026-11-28
Scope, source and reading notes
Management of open problem reports in the system, software, and airborne electronic hardware domains for type certification and TSO authorization.
Aerospace Consulting reference note: Provides a framework for assessing and managing unresolved problem reports and communicating their effects on certification findings.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 30042e1dfff49db2953e6683874baafdb912a9096900f3f62f3bb98ab3ba0b73
• Resolved – A problem report that has been corrected or fully mitigated, for which resolution of the problem has been verified but not formally reviewed and confirmed.
• Closed – A resolved problem report that underwent a formal review and confirmation
of an effective resolution of the problem.
4.3 Classification of PRs/OPRs
• ‘Significant’ – assessed at the product, system, or equipment level, a PR that has an
actual or potential effect on the product, system, or equipment function that may lead to a Catastrophic, Hazardous or Major failure condition, or may affect compliance with the operating rules.
• ‘Functional’ – a PR that has an actual or a potential effect on a function at the product, system, or equipment level.
• ‘Process’ – a PR that records a process non-compliance or deficiency that cannot result in a potential safety, nor a potential functional, effect.
• ‘Life Cycle Data’ – a PR that is linked to a deficiency in a life cycle data item but not
linked to a process non-compliance or process deficiency.
5. PROBLEM REPORT MANAGEMENT. The PR management process is a key enabler for OPR management. The PR management process enables the consistent and timely management of problems encountered across the system, software and AEH domains. Consequently, this process reduces the risk of a loss of visibility of critical issues remaining at the time of approval.
5.1 A PR management process across the system, software, and AEH domains should be established and used during the development (both for initial certification and subsequent changes) of a product or a TSO article. The PR management process should address the review and resolution of PRs that impact the transition to other development assurance processes.
5.2 A problem recorded after approval should also be managed through the PR management process, and any related systemic process issues should be identified and corrected.
5.3 PRs that cannot be resolved by the current stakeholder should be reported in a manner that is understandable to the affected stakeholders.
5.4 For PRs that may have an impact on other products or articles that are developed within an organization, a means should be established for sharing PR information so that any necessary corrective actions can be taken.
6. OPR MANAGEMENT. An OPR management process, based on the PR management process, should be established across the system, software, and AEH domains, including the following process steps:
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-189 and AMC 20-189 — published scope