AC 20-115D
Airborne Software Development Assurance Using EUROCAE ED-12( ) and RTCA DO-178( )
20-115D · 2017-07-21 Source checked 2026-11-28
Scope, source and reading notes
This AC recognises DO-178C/ED-12C, DO-330/ED-215 and the model-based, object-oriented and formal-methods supplements. Apply the relevant provisions to the software and certification context.
Aerospace Consulting reference note: Software development assurance and recognition of DO-178C/ED-12C, its supplements and tool qualification guidance.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: 5597a1af49c872a1a843c05601742ddcc8e8a190642f31e3cb9ce8e0dc63d91e
Figure 1 - Legacy Software Process Flow Chart
Intent to use software
previously shown to satisfy DO-178, DO-178A,
Conduct Change Impact Analysis
or DO-178B
See 9.b(4)
Evaluate software usage history, SDs, ADs, OPRs,
Determine tool
etc. See 9.b.(1)
Yes
Will there be new software tools or changes to tools?
qualification requirements. See paragraph 10.
See 9.b.(5)
No
No
Is the software usage history
Correct process deficiencies and document plan for
acceptable?
See 9.b.(1)
resolving related software deficiencies.
See 9.b.(1)
Yes
Yes
Did you upgrade the software baseline to DO-178C IAW paragraph
9.b.(2)(a),(b),or(c)?
See 9.b.(6)
No
Is the software developed
No
using DO-178B?
See 9.b.(2)
No
Yes
If MBD, OOT, or FM will be used, do processes support the technique IAW
applicable guidance?
See 9.b.(7)(a)
Yes
Yes
Is the DO-178B software level
Is the DO-178 or DO-178A software level
Yes
acceptable?
acceptable?
See 9.b.(2)
See 9.b.(2)
No
No
No
Have the software plans and environment been
properly maintained?
Upgrade software baseline
Upgrade software baseline
See 9.b.(7)(b)
including all processes & procedures using DO-178B
including all processes & procedures using DO-178C
or use DO-178C and
Yes
and DO-330. See 9.b.(2)(a) or (b)
DO-330. See 9.b.(2)(c)
Yes
Do you want to declare equivalence to
DO-178C? See 9.b.(7)(c)
No
Upgrade software baseline
Is the legacy system
including all processes & procedures using DO-178C
Yes
software to be
and DO-330.
See 9.b.(9)
modified? See 9.b.(3)
No
Change software and associated life cycle data using the same DO-178( ) version as
the original approval. For configuration data / PDI, use approved process or establish
Change software and associated life cycle data using
new process using DO-178C.
DO-178C, Section 12.1, and
See 9.b.(8)(a) & (b)
Original approval basis or baseline upgrade to DO-178C acceptable as approval basis.
applicable supplements.
See 9.b.(3)(a) or (b)
See 9.b.(6) & (9)
Acronyms ADs – Airworthiness Directives FM – Formal Methods IAW – In Accordance With MBD – Model-Based Development OOT – Object Oriented Technology OPRs – Open Problem Reports PDI – Parameter Data Item SDs – Service Difficulties
Note: References to EUROCAE documents are intentionally omitted for formatting purposes.
View figures, tables and original page layout

Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-115D and AMC 20-115D — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source