Appendix A gives an acceptable means for certain powered-lift under §21.17(b). These criteria are not universally applicable CFR requirements; establish the basis for the particular aircraft.

The source, within reach.

Search within this AC, jump to a source page, or download the complete saved publication.

Download saved FAA PDF ↓

Read the source

The document, within reach.

FAA source document

Printed page A-39

PDF page 48 of 64

Enlarge original ↗

Original source view; text reflow has not yet been reviewed

Original FAA AC 21.17-4, PDF page 48
AC 21.17-4 · A-39Open saved PDF here ↗
Extracted text for finding words

This extraction supports search. Read the original page for complete notation and layout.

07/18/2025                                               AC 21.17-4
                                                                        Appendix A

(h) The applicant must take the intended aircraft application into account when performing the
safety analysis.
(i) The results of the safety analysis, and the assumptions about the aircraft application used in
the safety analysis, must be documented in accordance with the requirements in PL.3305.
PL.3377 Ingestion.
(a) Rain, ice, and hail ingestion must not result in an abnormal operation such as shutdown,
power or thrust loss, erratic operation, or power oscillations throughout the engine operating
range.
(b) Ingestion from other likely sources (birds, hailstones, foreign objects—ice slabs) must not
result in unacceptable power or thrust loss or hazardous engine effects as defined in
PL.3375(g)(2).
(c) If the design of the engine relies on features, attachments, or systems that the installer may
supply, for the prevention of unacceptable power or thrust loss or hazardous engine effects as
defined in PL.3375(g)(2) following potential ingestion, then the features, attachments, or systems
must be documented in accordance with the requirements in PL.3305.
PL.3383 Vibration demonstration.
Each engine design must undergo a vibration survey to establish that the vibration characteristics
of those components subject to induced vibration are acceptable throughout the approved flight
envelope and engine operating range for the specific installation configuration. The possible
sources of the induced vibration that the survey must assess are mechanical, aerodynamic,
acoustical, internally induced electromagnetic, installation induced effects that can affect the
engine vibration characteristics, and likely environmental effects. This survey must be shown by
test, validated analysis, or a combination thereof.
PL.3384 Overtorque.
When approval is sought for a transient maximum engine overtorque, the applicant must
demonstrate by test, validated analysis, or a combination thereof, that the engine can continue
operation after operating at the maximum engine overtorque condition without maintenance
action. Upon conclusion of overtorque tests conducted to show compliance with this subpart, or
any other tests that are conducted in combination with the overtorque test, each engine part or
individual groups of components must meet the requirements of PL.3393.
PL.3385 Calibration assurance.
Each engine must be subjected to calibration tests to establish its power characteristics and the
conditions both before and after the endurance and durability demonstrations specified in
PL.3387 and PL.3390.
PL.3387 Endurance demonstration.
(a) The applicant must subject the engine to an endurance demonstration, acceptable to the
Administrator, to demonstrate the engine’s limit capabilities.
(b) The endurance demonstration must include increases and decreases of the engine’s power
settings, energy regeneration, and dwellings at the power settings and energy regeneration for
sufficient durations that produce the extreme physical conditions the engine experiences at rated

                                       A-39

Saved from the FAA on November 17, 2026. All original pages are retained. Engineering explanations are presented separately below.

Aerospace Consulting / Engineering perspective

Begin with the aircraft and the agreed basis.

Connect the operating concept, aircraft-level failure effects, system architecture and assurance planning. Keep FAA powered-lift criteria and EASA SC-VTOL provisions distinct when developing the safety and certification approach.

Explore our eVTOL safety and certification approach →
Source edition and reading coverage

64 original pages. 0 pages have reviewed text reflows. Original-first pages retain the source layout, with extracted text available for finding words.

Source SHA-256: e1a60e5f5ed4f34764beb0866a0a1b65471832a1cf169ef670a6dd6bf434297e

This is a dated source copy. Automatic source acquisition is not yet scheduled.

Original FAA PDF ↗

Working through a certification question?

Bring the aircraft, the basis and the issue your team needs to resolve.

Discuss your programme →