Appendix A gives an acceptable means for certain powered-lift under §21.17(b). These criteria are not universally applicable CFR requirements; establish the basis for the particular aircraft.

The source, within reach.

Search within this AC, jump to a source page, or download the complete saved publication.

Download saved FAA PDF ↓

Read the source

The document, within reach.

FAA source document

Printed page A-20

PDF page 29 of 64

Enlarge original ↗

Original source view; text reflow has not yet been reviewed

Original FAA AC 21.17-4, PDF page 29
AC 21.17-4 · A-20Open saved PDF here ↗
Extracted text for finding words

This extraction supports search. Read the original page for complete notation and layout.

07/18/2025                                               AC 21.17-4
                                                                        Appendix A

SUBPART E—POWERPLANT
PL.2400 Powerplant installation.
(a) For the purpose of this subpart, the aircraft powerplant installation must include each
component necessary for propulsion, which affects propulsion safety.
(b) Each aircraft engine and propeller must have a type certificate or be approved under the
aircraft type certificate using criteria found in subparts I and J. Engine-driven lift devices and
related engine structures necessary to transmit loads from the device to the airframe must also
comply with all applicable design load conditions and safety factors defined in subpart C.
(c) The applicant must construct and arrange each powerplant installation to account for—
(1) Likely operating conditions, including foreign-object threats;
(2) Sufficient clearance of moving parts to other aircraft parts and their surroundings;
(3) Likely hazards in operation including hazards to ground personnel; and
(4) Vibration, flutter, and fatigue.
(d) Hazardous accumulations of fluids, vapors, or gases must be isolated from the aircraft and
personnel compartments and be safely contained or discharged.
(e) Powerplant components must comply with their component limitations and installation
instructions or be shown not to create a hazard.
(f) Engine-driven lift devices and the engine, components, controls, and drive systems that
support those devices must be shown to have sufficient endurance and durability.
PL.2405 Power or thrust control systems.
(a) Any power or thrust control system or powerplant control system must be designed so no
unsafe condition results during normal operation of the system.
(b) Any single failure or likely combination of failures or malfunctions of a power or thrust
control system or powerplant control system must not prevent continued safe flight and landing
of the aircraft.
(c) Inadvertent flightcrew operation of a power or thrust control system or powerplant control
system must be prevented, or if not prevented, must not prevent continued safe flight and landing
of the aircraft.
PL.2410 Powerplant installation hazard assessment.
The applicant must assess each powerplant separately and in relation to other aircraft systems
and installations to show that any hazard resulting from the likely failure of any powerplant
system, component, or accessory will not—
(a) Prevent continued safe flight and landing or, if continued safe flight and landing cannot be
ensured, the hazard has been minimized;
(b) Cause serious injury that may be avoided; and
(c) Require immediate action by any crewmember for continued operation of any remaining
powerplant system.


                                       A-20

Saved from the FAA on November 17, 2026. All original pages are retained. Engineering explanations are presented separately below.

Aerospace Consulting / Engineering perspective

Begin with the aircraft and the agreed basis.

Connect the operating concept, aircraft-level failure effects, system architecture and assurance planning. Keep FAA powered-lift criteria and EASA SC-VTOL provisions distinct when developing the safety and certification approach.

Explore our eVTOL safety and certification approach →
Source edition and reading coverage

64 original pages. 0 pages have reviewed text reflows. Original-first pages retain the source layout, with extracted text available for finding words.

Source SHA-256: e1a60e5f5ed4f34764beb0866a0a1b65471832a1cf169ef670a6dd6bf434297e

This is a dated source copy. Automatic source acquisition is not yet scheduled.

Original FAA PDF ↗

Working through a certification question?

Bring the aircraft, the basis and the issue your team needs to resolve.

Discuss your programme →