Scope, source and reading notes

HIRF protection for aircraft electrical and electronic systems, including all three appendices.

Aerospace Consulting reference note: Provides the HIRF protection framework and supporting environmental, transfer-function and safety-assessment guidance.

Complete selected AMC and associated material, from PDF pages 518–559 of the AMC-20 consolidation. The original PDF contains the whole consolidation. Reading text is extracted; original figures and layout remain available.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b3d02d6ad4cd2833f79be85634221f52ea8bd90a84c733257193e4a60a2d536a

Source page 544 · PDF page 544

there may be several systems or equipment laboratory test plans, an aircraft test plan, or a similarity plan for selected systems on an aircraft.

1. Test plan

(a) A HIRF compliance test plan may include the equipment, system, and aircraft test objectives for the acquisition of data to support HIRF compliance verification. The plan should provide an overview of the factors to be addressed for each system test requirement.

The test plan should include:

1. the purpose of the test;

2. a description of the aircraft and/or the system to be tested;

3. system configuration drawings;

4. the proposed test set-up and methods;

5. the intended test levels, modulations, and frequency bands;

6. pass/fail criteria; and

7. the test schedule and test location.

(b) The test plan should cover Level A, B, and C systems and equipment, as appropriate. Level A systems may require both integrated systems laboratory tests and aircraft tests. Level B and Level C systems and equipment require only equipment laboratory testing.

(c) The test plan should describe the appropriate aspects of the systems to be tested and their installation. Additionally, the test plan should reflect the results of any analysis performed in the overall process of the HIRF compliance evaluation.

2. Analysis plan. A HIRF compliance analysis plan should include the objectives, both at system and equipment level, for generating data to support HIRF compliance verification. Comprehensive modelling and analysis for RF field coupling to aircraft systems and structures is an emerging technology; therefore, the analysis plan should be coordinated with the Agency to determine an acceptable scope for the analysis.

The analysis plan should include:

(a) the purpose and scope of the analysis;

(b) a description of the aircraft and/or the system addressed by the analysis;

(c) system configuration descriptions;

(d) the proposed analysis methods;

(e) the approach for validating the analysis results; and

(f) pass/fail criteria, including margins to account for analysis uncertainty.

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 20-158B

Related technical context

Engineering context
Evidence and scope

AC 20-158B and AMC 20-158A — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.