AC 20-166A
Issue Paper Process
20-166A Source checked 2026-11-28
Scope, source and reading notes
Applicant guidance on issue papers for type certification, type validation, TSO authorization, parts approvals, and related certification activities.
Aerospace Consulting reference note: Explains the applicant role in identifying, documenting, and resolving significant certification issues through the FAA issue-paper process.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: f143ca9ce46598aa889d1ef667d124fbba2dd53ac5ab2bc68f701511cb23ae13
11/06/2014 AC 20-166A
Advisors (CSTA), fully informed of the technical issues encountered throughout the evaluation process.
i. The PM typically obtains accountable directorate assistance in formulating the “FAA POSITION” and “CONCLUSION” before the IP is submitted to the project team members for coordination. Directorate team coordination and standards staff manager sign-off on the IP is required at any stage of the IP that will be released to the applicant.
j. All new or revised IPs are coordinated with the applicant, the project team members and the accountable directorate. If coordination with the applicant and project team members happens without impasse, the PACO will close the IP by revising it and will then coordinate it with the accountable directorate without holding a formal TCBM. If the applicant is not satisfied with the conclusion reached through the IP process, further discussions, correspondence, or appeals must focus on new information or proposals. See subparagraph 7.m. for more information.
k. If an impasse occurs between TCB members, the PACO manager and/or directorate management must resolve it after considering the views of all affected parties. The resulting decision becomes the basis for the FAA position in the IP, which is signed by the designated representative of the accountable directorate.
l. Before completing the "CONCLUSION” of the IP at Stage 4, the FAA will make every effort to get an agreement with the applicant on the final requirements. These final requirements will be stated in the "CONCLUSION" at Stage 4. If further discussions require a revision to the applicant’s position, the applicant should submit his statements on a separate document or letter and the FAA will revise the IP accordingly and respond with a new position. For each revision, the PACO coordinates it with the appropriate project team members, the accountable directorate, and policy offices, if appropriate.
m. Approval by the accountable directorate of the “CONCLUSION” statement constitutes definition of the FAA requirement. The IP may be sent to the applicant directly or through the CA, for foreign projects. If coordination with the applicant and project team members happens without impasse, the PACO will close the IP. If the applicant is not satisfied with the conclusion reached through the IP process, further discussions, correspondence, or appeals must focus on new information or proposals. FAA’s responses to such efforts must refer to the current stage and date of the IP as well as indicate whether the new effort provides new information warranting a reconsideration of, and revision to, the IP; otherwise the IP “CONCLUSION” stands as written.
n. Generally, the FAA does not provide draft copies of IPs to applicants. However, the FAA may need the applicant’s help in developing the IP. For example, the FAA may request the applicant’s help to confirm the technical correctness of the “BACKGROUND.” Also, it may be necessary for the applicant to review his position as written in the IP to determine its accuracy.
o. If the applicant does not comply with the criteria of an IP, the project will not be closed and the approval will not be issued.
8
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-166A and AC 20-174 — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source