Applicant guidance on issue papers for type certification, type validation, TSO authorization, parts approvals, and related certification activities.
Aerospace Consulting reference note: Explains the applicant role in identifying, documenting, and resolving significant certification issues through the FAA issue-paper process.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: f143ca9ce46598aa889d1ef667d124fbba2dd53ac5ab2bc68f701511cb23ae13
11/06/2014 AC 20-166A
6. What Applicants Need to Know During the IP Process.
a. For applicants seeking a TC, STC, PMA, TSOA, or other type design approval, FAA technical personnel will work closely with the applicant to identify any significant issues that may require a special emphasis for resolution. This step will usually require more detailed technical discussions, correspondence, review of design data and hardware.
b. The FAA encourages the applicant to raise questions or issues that may require extra time or special study for resolution so all significant issues are identified as soon as practicable to allow sufficient time for resolution.
c. An IP is not required to document a particular MoC that is consistent with existing directives, ACs, or other written FAA policy, or that does not fall into one of the common types of IPs covered in paragraph 5.
d. Routine items relative to showing compliance and work relationships would not normally be raised as significant issues and would not require IPs unless some special problems are anticipated or develop during the course of the program. Decisions and actions will be documented in correspondence, data submittals, and file records of meetings, conversations, and events. In this regard, it is recognized that what may be routine with an experienced applicant may be treated as a significant issue with an applicant who has limited or no current FAA type certification experience.
e. An Organization Designation Authorization (ODA) holder may not approve IPs. When necessary, the FAA will develop IPs and the ODA administrator must cooperate with the FAA in this process and provide a company position when requested. The ODA procedures manual establishes the procedures necessary for ODAs to coordinate IPs.
7. IP Development. This section covers the development process for IPs related to type certification projects and type validation programs. See figure 1 below for the IP process flow chart and appendix A for a typical IP format. See appendix B for a description of the roles and responsibilities of the FAA personnel in the issue paper process and see appendix C for a list of commonly used terms and definitions.
a. For type certification projects, new IPs can be proposed to the TCB by the standards staff specialists, the project officer (PO), the program/project manager (PM), or by technical specialists for technical issues in their areas, through the PM. This can occur at any time during the process but before final type certification. For ODA projects, the OMT can propose new IPs (this also applies to the Delegation Systems Certification Office (DSCO)). The originator will enter the general information, the “STATEMENT OF ISSUE” and the “BACKGROUND” information in the IP at Stage 1. The PM must coordinate the “BACKGROUND” and “STATEMENT OF ISSUE” with the accountable directorate specialists through the PO. When a significant issue pertains to technical policy or avionics (for example, NextGen technologies) overseen by the Systems and Equipment Standards Branch (AIR-130), or a significant issue pertains to operational or maintenance suitability requirements overseen by the AEG offices, the
6
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 20-166A and AC 20-174 — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source