Applicant guidance on issue papers for type certification, type validation, TSO authorization, parts approvals, and related certification activities.

Aerospace Consulting reference note: Explains the applicant role in identifying, documenting, and resolving significant certification issues through the FAA issue-paper process.

The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: f143ca9ce46598aa889d1ef667d124fbba2dd53ac5ab2bc68f701511cb23ae13

Source page 17 · PDF page 17

11/06/2014 AC 20-166A Appendix B

• Obtains accountable directorate concurrence and approval of the IP,

• Develops the conclusion and transmits it to the applicant, and

• Places results in the official project file.

11. Project ACO (PACO). The PACO is the ACO working a certification project. The PACO may need to coordinate with the CMACO if the project is a follow-up certification activity such as an STC or PMA.

12. Project Team. The project team normally for an aircraft certification project usually consists of the following:

• A PM,

• Engineers or technical specialists,

• Flight test pilots and flight test engineers,

• Manufacturing inspectors,

• AEG operations and airworthiness inspectors, and

• A project officer and other persons at the discretion of the accountable directorate.

Note 1: The certification project team is comprised of the individuals needed to conduct a certification project. A TCB is an FAA management team (see appendix C).

Note 2: For engine or propeller certification projects, the project team composition could be slightly different.

13. Project Officer. The project officer (PO) provides regulatory or policy input to the project team or TCB through the PM and routes the IP through the accountable directorate’s specialists and manager, in order to keep them apprised of the issue and to obtain their concurrence. Quite often the PO acts as the PM for validation projects.

14. Technical Specialist. For type certification projects, new IPs can be proposed to the TCB by technical specialists for technical issues in their areas, through the PM, at any time during the process before final type certification.

15. TCB or Project Team. The TCB is the FAA management team responsible for acquainting the applicant with the certification process, resolving significant problems, processing and coordinating issue papers, and establishing a schedule for the overall accomplishment of the type certification project. A TCB is established only for projects of a certain magnitude. When a TCB

B-3

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 20-174

Related technical context

Engineering context
Evidence and scope

AC 20-166A and AC 20-174 — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.