Aircraft electrical and electronic system lightning protection, including both appendices.

Aerospace Consulting reference note: Provides guidance for assessing lightning effects, assigning protection levels and demonstrating protection of aircraft electrical and electronic systems.

Complete selected AMC and associated material, from PDF pages 464–496 of the AMC-20 consolidation. The original PDF contains the whole consolidation. Reading text is extracted; original figures and layout remain available.

Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.

Official source recordOriginal PDF on this site

Source: EASA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: b3d02d6ad4cd2833f79be85634221f52ea8bd90a84c733257193e4a60a2d536a

Source page 486 · PDF page 486

certification plan accordingly. The updated certification plan shall be resubmitted in accordance with point 21.A.15(c) to the Agency for acceptance.

9. LIGHTNING COMPLIANCE DEMONSTRATION

a. Lightning compliance plan. An overall lightning compliance plan should be established to clearly identify and define lightning certification specifications, lightning protection development, and the design, test, and analysis activities intended to be part of the compliance effort. This plan should provide definitions of the aircraft systems, installations, and protective features against which lightning compliance will be assessed. The lightning compliance plan should be discussed with, and submitted to, the Agency for acceptance before initiating lightning compliance activities. If the aircraft, system, or installation design changes after approval, a revised lightning compliance plan should be submitted to the Agency for acceptance. The lightning compliance plan should include the following:

1. a lightning compliance plan summary;

2. identification of the aircraft systems, with their classifications based on the safety assessment as it relates to lightning (see paragraph 6(c)(2));

3. the planned or expected lightning environment for installed systems; and

4. the verification methods, such as test, analysis, or similarity.

b. Methods of compliance verification

1. Various methods are available to aid in demonstrating lightning compliance. Methods acceptable to the Agency are described in Sections 7 and 8 of this AMC. Figure 2 above outlines the steps to lightning compliance for systems requiring Level A lightning certification. Figure 3 above outlines the steps to lightning compliance for systems requiring Level B or Level C lightning certification. The steps in these figures are not necessarily accomplished sequentially. Wherever a decision point is indicated on these figures, the applicant should complete the steps in that path as described in Sections 7 and 8 of this AMC.

2. Other lightning compliance techniques may be used to demonstrate system performance in the lightning environment; however, those techniques should be accepted by the Agency before using them.

c. Lightning verification test, analysis, or similarity plan. Test, analysis and similarity are all acceptable methods. The applicant must choose the method or the combination of methods most appropriate for their project. See Sections 7 and 8 of this AMC, and SAE ARP 5415B / EUROCAE ED-158 for additional guidance for selecting the appropriate method. Specific lightning test, analysis, or similarity plans could be prepared to describe specific verification activities. A single verification plan combining various methods for all the selected systems or dedicated verification plans may be necessary. For example, there may be several systems or equipment laboratory test plans, an aircraft test plan, or a similarity plan for selected systems on an aircraft.

Connected references

Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.

AC 20-136C

Related technical context

Engineering context
Evidence and scope

AC 20-136C and AMC 20-136A — published scope

Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.

This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.

Supporting source

Copy reference

Select and copy the citation below.