AC 25.1329-1C
Approval of Flight Guidance Systems
25.1329-1C — Changes 1–2 incorporated (2026-02-13) Source checked 2026-11-28
Scope, source and reading notes
Flight-guidance-system compliance under § 25.1329 for transport category airplanes; includes autopilots, flight directors, automatic thrust control, and associated interactions. Base publication catalog date: 2014-10-27; latest included change: 2026-02-13.
Aerospace Consulting reference note: Guidance for flight-guidance design and approval, incorporating Changes 1 and 2, including 2026 clarifications concerning disengagement alerts, override hazards, and incompatible modes.
The complete selected publication is available in reading text and as the original PDF. Reading text is extracted from the official PDF; page layout is simplified, and figures and tables should be checked in the original page view.
Search covers extracted text. Words contained only in graphics may not be searchable. The original publication is available below.
Official source recordOriginal PDF on this siteSource: FAA. Reproduced with source acknowledgment; source edition and status are shown above. SHA-256: d1122e89d61663cc44456dd1ebff460127469027d8d667b0fd695bc8436357e0
AC 25.1329-1C CHG 2
(5) Pilot recovery.
(a) Pilot recovery action. The recovery action should be commenced after the reaction time. Following such delay, the pilot should be able to return the airplane to its normal flight attitude under full manual control without engaging in any dangerous maneuvers during recovery and without control forces exceeding the values given in § 25.143(d). During the recovery, the pilot may overpower the autopilot or disengage it.
(b) Minimum autopilot use height. For the purpose of determining the minimum height at which the autopilot may be used during an approach or for height loss assessments, a representative pilot recovery maneuver appropriate to the airplane type and flight condition should be performed. This maneuver should not lead to an unsafe speed excursion to resume a normal flight path. An incremental normal acceleration in the order of 0.5 g is considered the maximum for this type of maneuver.
c. Takeoff.
(1) Worst-case failure condition. The primary concern for the takeoff phase of flight is the effect of the worst-case failure condition identified by the safety assessment on the following:
(a) The net effect on the flight path of the airplane after takeoff, and
(b) The airplane’s attitude and speed during climbout.
(2) Failures to be evaluated. Failures that would cause the airplane to pitch up, pitch down, and bank during the takeoff should be evaluated, if those failure conditions exist (given the architecture of a specific FGS) and are relevant to the safety assessment.
(3) On runway guidance. If the FGS provides on runway guidance for takeoff, the effect of any failures of that takeoff guidance should be assessed. See AC 20-191 for additional information.
d. Climb, cruise, descent, and holding. Where the safety analysis identifies a failure condition requiring flight/simulator evaluation with pilot assessment, the height loss should be established in accordance with the method described in AC 25-7D, paragraph 33.7.10.5.4, Assessment of Approach without Vertical Path Reference.
e. Maneuvering. Where the safety analysis identifies a failure condition that has a dynamic effect on the roll control of the airplane, the failure condition should be introduced at the bank angle for normal operation. The bank angle should not exceed 60 degrees when the pilot recognition and the recovery times identified above are applied.
f. Approach. A discussion of the operational considerations for approach operations is contained in paragraph 101, Criteria Supporting Operational Use of Autopilot. This chapter identifies test criteria to support those considerations. The safety assessment process should identify the demonstration of specific failure conditions during the approach. The fault demonstration process during approach should include the four phases identified in
Connected references
Source-backed citations and subject-based engineering context are labelled separately. These links do not establish equivalence or project acceptance.
Related technical context
Engineering contextEvidence and scope
AC 25.671-1 and AC 25.1329-1C — published scope
Aerospace Consulting navigation suggestion based on the subject and stated scope of the two publications.
This connection does not establish regulatory equivalence, acceptance of a newer edition, or applicability of a project-specific precedent to another programme.
Supporting source